7 | Maintenance
22 / 36
Instruction Manual Supplement DOLPHIN VL Systems ATEX_EN_en
7
Maintenance
WARNING
Machines contaminated with hazardous material.
Risk of poisoning!
Risk of infection!
If the machine is contaminated with hazardous material:
• Wear appropriate personal protective equipment.
CAUTION
Hot surface.
Risk of burns!
• Prior to any action requiring touching the machine, let the machine cool down first.
• Shut down the machine and lock against inadvertent start up.
• Turn off the operating liquid system.
• Vent the connected lines to atmospheric pressure.
If necessary:
• Drain the operating liquid
• Disconnect all connections
7.1 Maintenance Schedule
The maintenance intervals depend very much on the individual operating conditions. The
intervals given below are considered as starting values which should be shortened or ex-
tended (except safety component tests) as appropriate. Particularly harsh applications or
heavy duty operation, such as high dust loads in the environment or in the process gas,
other contamination or ingress of process material, can make it necessary to shorten the
maintenance intervals significantly.
Interval
Maintenance Work
Daily
• Check the machine for leaks, in case of leaks have the
machine repaired (contact Busch).
• Check vacuum pump bearing condition, tempera-
ture / audible noise.
• Check vacuum pump for audible cavitation noise.
Yearly
• Test all safety components to ensure they are func-
tioning correctly. Document the test, replace it if
damaged.
• Clean Y-strainer.
• Clean inlet screen if installed.
• Drain and clean level indicator.
• Flush and clean heat exchanger.
• Check function of electrical control devices.
Summary of Contents for DOLPHIN VL 0100 A
Page 34: ...Note...
Page 35: ...Note...