X7-8-Install-IG100 Installation Guide
Brocade
®
X7-8 Director Hardware Installation Guide
4. Enter the
chassisEnable
command to enable all user ports in the chassis and enable a virtual, fabric-aware
chassis.
5. Replace the chassis door. The door is required to meet EMI compliance.
6. Pack the faulty CP blade in the packaging provided with the new CP blade, and contact the switch supplier to
determine the return procedure.
Verifying Blade Operation
Perform the following tasks to verify operation of new blade:
1. Check the LED indicators on the blade's front panel. For information on interpreting LED patterns, see
2. Enter the following commands and note any error conditions:
•
slotShow
– Displays the current data on each slot in the system, including blade type, blade ID, status, Brocade
model name, and power usage.
•
haShow
– Displays control processor (CP) status.
•
tempShow
– Displays temperature reading of blades.
•
sensorShow
– Displays temperature reading of blades with fan and power supply status.
•
errDump
– Displays the entire system error log.
•
errShow
–Displays error log messages one at a time.
See
Brocade Fabric OS Command Reference Manual
for output
examples and additional information on Fabric OS commands. For more information about error messages,
refer to the
Brocade Fabric OS Message Reference Manual
.
X7-8-Install-IG100
150