Not for
Reproduction
32
INSTALLATION
cont.
A
A
A
Figure 23
Control Box Cover
NOTICE
It may take a few minutes to purge the
gaseous fuel lines when the generator
is started for the first time
Initial Start-Up (No Load)
The generator has been configured for NG operation at the
factory.
Fuel conversion, if needed, must be completed prior to
performing these steps. See
Fuel Conversion.
Before operating the generator or placing it into service,
inspect the entire installation carefully. Then begin testing
the system without any electrical loads connected, as
follows:
1.
Remove three screws (
A
) that secure control box cover
to enclosure. Remove control box cover to expose
generator’s circuit breaker.
2.
Connect an accurate frequency meter to line side of
generator’s main circuit breaker.
3.
Set generator’s main circuit breaker to
ON
(closed)
position.
4.
Verify manual shutoff valve is open.
5.
Install 15A fuse in control board.
6.
Press and hold
MANUAL
button on control board for 3
seconds. Engine will start.
7.
Listen for unusual noises, vibration or other indications
of abnormal operation. Check for oil leaks while engine
runs.
8.
Let engine warm up for 5 minutes to allow internal
temperatures to stabilize.
9.
Check generator output at load side of circuit breaker.
Voltage should be 215 - 240 Volts, frequency should be
49.0 - 51.0 Hz.
10.
Check generator output voltage between one generator
connection lug then between other generator connection
lug. In both cases, voltage reading should be between
215 and 240 Volts.
11.
Push and hold
OFF
button on control board until engine
stops.
12.
Reinstall control box cover.