Commissioning
Notes
–
Commissioning and the functional test may only be carried out by authorized specialist
personnel.
–
Observe all country-specific testing and acceptance regulations.
–
A functional test must be carried out before commissioning.
Bosch recommends at least one functional test and one visual inspection per year.
–
Follow the shut down procedure specified in the user guide, before removing the power
from the panel or remote keypad.
Documentation
The current and full product documentation can be found at www.boschsecurity.com
(Installation guides, System information, User guide).
The fire panel is configured on a PC using the FSP-5000-RPS programming software. The
programming software and the associated documentation can be found at
www.boschsecurity.com for those with access rights.
Information about the programming software is also included in the FSP-5000-RPS online
help.
Guide for Commissioning
1.
Connect the panel to the power supply.
2.
Calibrate the touchscreen by pressing precisely on the cross-hairs.
3.
Enter time, date, PNA (Physical Node Address), Ethernet Settings and reboot the panel.
4.
Connect the panel controller to the PC (via USB). Make sure that the current version of
the FSP-5000-RPS programming software is installed on your PC.
5.
Start the auto-configuration. Edit the configuration according to the requirements of the
fire alarm system.
6.
Load the configuration to the panel controller.
7.
Start the walktest.
8.
Now go further with:
–
Testing the power supply
–
Testing the conventional and LSN functions
–
Testing the addressing/activation
9.
Read out the diagnosis file and save the file as a test log.
5.1
Functional test
All components of the fire alarm system are installed and wired.
Switch on the fire panel by pressing the power button. The touchscreen calibration procedure
will start automatically if necessary. For the initial setup of the panel, you have to enter time
and date, physical node address, and Ethernet settings like redundancy and IP address. To
make all changes effective you have to reboot the panel. For further information refer to the
AVENAR panel series user guide.
1.
Connect the laptop on which the FSP-5000-RPS programming software is installed to the
fire panel.
2.
Load the configuration.
3.
Now go further with:
–
Testing the power supply
–
Testing the conventional and LSN functions
–
Testing the addressing/activation