background image

 10 

 

                                               2005 Boreal Geothermal Inc. 

www.boreal-geothermal.com 

Horizontal Trench Requirements 

 
The ACDX heat pump requires one groundcoil or "loop" 

per nominal ton of capacity.  

 
Trenching for the ACDX heat pump can be best accom-

plished with a tracked excavator equipped with a 44” to 48” 
bucket. If a wider bucket is available and you can afford the 
extra cost, the trenches could be wider for improved perform-
ance. 

The object, of course, is to allow the copper loops to 

contact earth which has not been influenced by the prox-
imity of another loop.

 The trenches are dug from 5 to 6 ft. 

deep to a total length of 180'.  Each of the ACDX  loops is 
350' long and when laid in the form of a U down each side of 
the trench the turn at the end will occur at 175' allowing for a 
small degree of error by the excavator operator.  Take special 
care that the bottom of the trench is kept as smooth as possi-
ble to reduce the chance of pinching or crushing the copper 
tubing when backfilling the trench. If rocky conditions are 
encountered it is recommended that the bottom of the trench, 
especially the corners where the pipe will lay, be covered by 
hand with limestone tailings,  or some other heavy dense ma-
terial t provide a relatively smooth resting place for the cop-
per pipe. Unlike plastic pipe, the copper tubing will stay 
where you put it when unrolled rather than arguing with you, 
as plastic does, on a cool day. Once the pipe has been un-
rolled and placed, backfilling by hand to a depth of 4-6" with 
fill as described above will ensure that the pipe is protected 
from falling rock etc. during the machine backfilling proce-
dure. 

 
Other excavating devices such as a ditch-witch (chain 

digger) or a regular back-hoe can be used if ground conditions 
permit however you will have to dig a U shaped trench with 
spacing 5 ft.  to 10 ft.. We have found that the greater speed 
of the tracked excavator in most soil conditions and the fact 
that you only have to dig one trench (which is excellent width 
for a man to work in) more than compensates for it's extra 
rental or operational costs. 

 
An alternative technique for burying the underground cop-

per tubing would be to dig a large shallow pit with a bull-
dozer. This pit would have to be large enough to accommo-
date all the loops required in the system. The copper tubes 
should have a spacing of at least 6 ft. minimum. A wider 
spacing would lead to slightly greater efficiency.  

Entering dwelling 

 

The copper ground loops must enter the dwelling at some 
location typically through the concrete foundation just above 
the poured floor. An alternate method would be to run the 
pipe (insulated) up the outside wall making a 90 degree turn 
above ground and entering the dwelling between the floor 
joists just below the first floor. These pipes should be insu-
lated with a minimum of 3/4" of closed cell weatherproof  

insulation. There will be two 1/2" OD copper tubes for each 
nominal ton of capacity of the heat pump being installed. For 
example a 3-ton unit would have 3 groundloops and thus 6 
ends to go through the concrete wall. We recommend that you 
drill these holes to a diameter large enough to allow for the 
insertion of a plastic sleeve, (see drawing ) and the tubing 
with it's insulation jacket. Suitable measures must be taken to 
seal the installation from water penetration before the trench 
is backfilled. 

Unrolling & placing the Tubing 

 
Each 50' roll of tubing is taped both individually and to 

the next roll in the group so that at any one time only 50' of 
the 350' is free to unroll. This allows for easier unrolling and 
prevents kinking the pipe. Observe how the taping is done so 
that you know which side of the loop to start unrolling first.  

 
To begin, unroll approximately 12' of copper tubing. Slide 

two 6' lengths of armaflex closed cell insulation with wall 
thickness of at least 1/2”over the end of the tubing and insert 
it  through the plastic sleeve of hole # 1 approximately 8" into 
the basement. It is good practice to label this line 

"loop 1 - 

gas" 

to identify it when interconnecting linesets inside the 

building. Unroll the copper tubing down one corner of the 
trench. When 175 ft of tubing has been laid out make your 
turn and proceed back the other side of the trench to the foun-
dation of the building. Slide two 6' lengths of armaflex insula-
tion onto the tubing and insert the stub end through hole # 2 in 
the wall to match the other end of the loop. Label this end of 
the line 

"loop 1 - liquid"

 so that the complete loop can be 

identified later. Manually backfill the loop with fill to a depth 
of 4 to 6" for protection during the machine backfill process. 
Duplicate the process described above applying labels to 
identify the two ends of successive loops (loop 2,3,4 etc.) 
until all required loops are in place.     

Insulation placement near foundation 

 
It is important to apply closed cell insulation to the copper 

ground loops as they come within 12' of the building to pre-
vent the possible build up of ice near the foundation of the 
home. Applying 1/2” wall closed cell waterproof insulation to 
the tubing as described above will insure that very little heat 
is absorbed from the ground near the basement wall thus 
avoiding possible frost damage to the structure.  

Pressure testing linesets 

Using the 1/4" schrader valve supplied on each loop the 

installer can again check the pressure on each lineset with his 
refrigeration gauge set before releasing the pressure and cut-
ting the loop stubs coming into the basement to the proper 
lengths. 

Summary of Contents for ACDX-45

Page 1: ...ermal com Installation Manual ACDX 45 55 65 High Efficiency Direct Expansion Geothermal Heat Pumps Energy Efficient Solutions Tel 514 886 0682 Fax 514 221 3448 Email info boreal geothermal com Web www boreal geothermal com Boreal GEOTHERMAL Inc ...

Page 2: ...ged from this unit must be recovered WITHOUT EXCEPTION Technicians must follow industry accepted guidelines and all local state and federal statutes for the recovery and disposal of refrigerants If a compressor is removed from this unit refrigerant circuit oil will remain in the compressor To avoid leakage of the compressor oil refrigerant lines of the compressor must be sealed after it is removed...

Page 3: ...11 Built in refrigerant safety controls 13 Theory of Operation 15 Vertical Case Dimensions 18 Horizontal Dimensions 19 20 Electrical Requirements Component Layout 21 Performance Ratings 22 CFM available 23 Trouble Shooting Guide 24 Electrical Schematic 27 Installer Wiring 28 Plenum Heater Wiring 29 Duct sizing Guide 30 Warranty 35 Section Page Electronic Control Board 31 ...

Page 4: ...ll be sufficient moisture present in the loop field area during the summer a soaker hose is recommended in all hori zontal trench systems which will used for air condi tioning purposes Vertical Bore Systems Vertical bores 3 x 100 ft holes provide an alternate method of installing a ACDX unit A high water table in the borehole area 20 to 30 ft will insure that there is adequate conduction with the ...

Page 5: ...e installed to prevent the build up of pressure which may result in bursting of the circulator pump housing if the unit is operated while both valves are shut See point A marked above Boreal ACDX All Models Hot water lines are 1 2 ID copper Insulate both hot lines and all refrigerant lines Use ball or gate valves on hot water lines Set hot water thermostats in tank to 120 F Use flexible duct colla...

Page 6: ...or residential and commer cial uses These attempts have failed adequately to meet a num ber of requirements associated with an economically and func tionally viable system Some of the shortcomings included I Inadequate oil return to the compressor primarily in the heating mode II Inadequate evaporator length and spacing for properly ex tracting heat from the earth resulting in low capacity and low...

Page 7: ...should be same as it was originally Insulate both liquid lines and vapor lines from the heat pump to the well head unless in separate horizontal trenches Vapor lines in separate horizontal trenches need only be insulated from 10 ft out in the trench to the basement wall Liquid lines must be insulated from the heat pump to approx 6 ft down the drop pipes in the vertical boreholes Install spacers to...

Page 8: ...wood The styrofoam will smooth out any irregularities in the cement floor while the plywood will distribute the weight of the BOREAL unit evenly over the styrofoam This process will also deaden the compressor noise emitted from the bottom of the cabinet As an alternative several pieces of 2 x 4 lumber can be placed under the unit running from the electrical connection side to the filter rack side ...

Page 9: ...9 2005 Boreal Geothermal Inc www boreal geothermal com Piping Layout of a BOREAL Vertical ACDX Heat Pump System ...

Page 10: ...making a 90 degree turn above ground and entering the dwelling between the floor joists just below the first floor These pipes should be insu lated with a minimum of 3 4 of closed cell weatherproof insulation There will be two 1 2 OD copper tubes for each nominal ton of capacity of the heat pump being installed For example a 3 ton unit would have 3 groundloops and thus 6 ends to go through the con...

Page 11: ...11 2005 Boreal Geothermal Inc www boreal geothermal com BOREAL ACDX Horizontal Trench Design ...

Page 12: ...uuming the system with a leak will be impossible and attempting to do so will introduce moisture to the system making the process take much longer to vacuum after the leak has been found and re paired vacuum the system until the reading on an electronic vacuum gauge stays below 500 microns for a period of 5 minutes after the vacuum pump is shut off and the system sealed Charging system Once the sy...

Page 13: ...13 2005 Boreal Geothermal Inc www boreal geothermal com BOREAL Horizontal ACDX Heat Pump System Plan View ...

Page 14: ... of water total Return ducts should ide ally be placed in every room and be sized 50 larger than corresponding supplies In some instances the number of floor diffusers will actually double when compared to the number that would normally be used for a warm air oil fired furnace Starting the Heat Pump BEFORE starting the heat pump the following areas should be rechecked to assure proper operation 1 ...

Page 15: ... of 1 2 copper tubing The pit could be a excavated area or an existing area which needs to be filled as part of general excavation Loops should be buried approxi mately 6 ft underground for best performance Example Boreal ACDX 45 should have 3 loops as shown at left a ACDX 55 4 loops and a ACDX 65 5 loops Other configurations would work as well such as a 50 ft x 50 ft pattern or a 60 ft x 45 ft et...

Page 16: ...oop by virtue of the sensing bulbs being attached to each respective return vapor line and all the equalizer lines con nected to the common suction inlet line The sensing bulb of each TX valve is located just below the connection to the 3 way valves on the gas line header assembly The liquid refrigerant coming in contact with the warm earth vaporizes to a gas and flows back to the heat pump via th...

Page 17: ...itch from heating to cooling mode without shut off on it s low pressure control since refrigerant pressure is supplied to the intake of the com pressor by the idle loops while the refrigerant is being repositioned to operate in another loop or loops Once the refrigerant enters the ground loop s it con denses giving up its heat and returns to its liquid state Oil and liquid refrigerant are swept al...

Page 18: ...18 2005 Boreal Geothermal Inc www boreal geothermal com BOREAL Series ACDX 45 55 65 Engineering and Performance Data ...

Page 19: ... acoustic material Supply Return Duct Sizes Basic cabinet design is the same for all ACDX mod els 45 55 65 Cold air return measures 27 x 30 5 Hot air plenum can be attached to any point on top of the unit except within 6 of the filter rack To pro tect the air coil below See the line marked A at left Filter rack is removable to facilitate easy entry to the building and is reversible so that the fil...

Page 20: ...ng 13 5 x 15 5 14 00 3 19 2 00 16 15 BLOWER DOOR FRONT VIEW FRONT DOOR SIZE 28 W x 31 H 1 25 1 00 31 00 1 00 4 22 4 00 3 50 3 50 4 50 7 50 5 00 5 00 33 00 17 13 6 99ø RIGHT SIDE DOOR 26 07 2 50 BACK SIDE Return Air Side 19 00 Electric Box 1 00 18 00 DOOR Filter rack area Refrigerant Air Coil 33 00 29 00 52 00 27 00 33 00 Direct Expansion to Air Heat Pumps Cabinet Piping Layout horizontal ...

Page 21: ...Size 40 40 50 Max breaker size 40 40 50 Thermostat wire size 18 18 18 Thermostat conductors 8 8 8 Domestic Hot Water Generator Specifications Temperature IN F Temperature OUT F Temperature Rise F of Total ACDX 45 Igal hr ACDX 55 Igal hr ACDX 65 Igal hr 40 150 110 20 10 11 8 14 5 45 150 105 18 9 4 11 1 13 7 50 150 100 15 8 33 9 8 12 1 60 150 90 12 7 33 8 6 10 6 75 150 75 10 7 33 8 6 10 6 90 150 60 ...

Page 22: ...elt drive blower with ball bearings Non sticking reversing valve High efficiency ball bearing PSC style motor Galvanized drip tray Sight glass optional Suction accumulator Bi flow filter driers Thermostatic expansion valve Front Plumbing side Back Electrical Box Side Baked enamel cabinet with satin galvanized condensate tray and floor Components accessible from three sides Heavy duty electrical co...

Page 23: ...ip BM HE 33 Marathon G 10 Blower 2 row 6 circuit air coil 1 2 x 210 ft loops 41 Heating Voltage 230 1 60 Entering Air 70DB 60WB CFM 1550 External Static 15 WC 1 2 x 210 ft loops 77 Cooling Capacity Data Model ACDX 55 HAC nominal 4 ton Heating Ground Temp Heat of Absorption EAT LAT Diff Btu s Out Comp Amps Comp Watts Blower Amps Blower Watts Total Watts COP Suct Disc Pres 70 60745 70 111 4 41 6 708...

Page 24: ... 14 41 9 207 2 30 30341 70 96 7 26 7 49725 22 2 4491 4 2 412 4903 2 97 38 8 203 5 Ground EAT LAT Diff Sens Latent Total Comp Comp Blower Blower Total EER Suct Disc 50 79 9 56 7 23 15 42405 22950 65355 25 9 4342 4 5 415 4757 13 7 66 7 185 7 60 79 9 58 1 21 79 39878 23849 63727 27 4 4415 4 4 420 4835 13 2 70 0 211 6 70 79 5 58 2 21 20 38940 19443 58383 28 4 4515 4 3 415 4930 11 8 69 8 234 8 77 80 1 ...

Page 25: ... power company Burned out motor Ohmmeter shows no resistance be tween common and run terminals or between common and start terminals Note Be sure compressor overload has had a chance to reset If comp is hot this may take several hours Determine cause and replace motor Thermal overload on com pressor tripped Ohmmeter shows reading when placed across R and S terminals and infinity between C R or C S...

Page 26: ...arily until room comes up to temperature Faulty low pressure ctrl Refrigerant pressure control should open on drop at approx 20 psig Control should reset automatically Heat pump can then be restarted by resetting the lock out relay Turn power off then back on Replace faulty control if it will not reset Low refrigerant charge Check return air temp Normal suc tion is 40 60 psig Add refrigerant slowl...

Page 27: ...ter heat exchanger Check water flow and power to pump Check water lines for obstruc tion Remove obstruction in water lines Acid treat the domestic hot water coil Thermostat limit is open Check contact operation Should close at 120 F and open at 140 F Replace thermostat if faulty Disconnect switch open or fuse blown in electrical sup ply to hot water tank Check both line and load sides of fuses If ...

Page 28: ...28 2005 Boreal Geothermal Inc www boreal geothermal com BOREAL ACDX Series Schematic Wiring Diagram Package Unit Schematic Shown ...

Page 29: ...t on off Hot Water Circulator Special Instructions Note If heat pump is to be operated without the hot water circulator connected to the water tank and flooded with water remove the wire marked with RED tape located here This pump is water lubricated and must not be run dry 230 115v 1 60 connections Wire to lugs on compressor relay Connect L3 to Black Connect L2 to White neutral Connect L1 to Red ...

Page 30: ...ng the remaining 2 conductors connect F and F in the heat pump s electrical box to F and F in the plenum heater Thermostat Operation The BOREAL heat pump comes supplied with a 2 stage heating 1 stage cooling auto change over digital thermostat The heat pump is already prewired for this stat and requires only the connections mentioned above for full operation The thermostat operates the heat pump a...

Page 31: ...x 40 10 x 30 12 x 24 14 x 20 16 x 17 16 5 x 16 5 20 1750 2000 18 8 x 40 10 x 30 12 x 24 14 x 20 16 x 17 16 5 x 16 5 22 2000 2250 20 10 x 38 12 x 30 14 x 26 16 x 22 18 x 19 18 5 x 18 5 22 2250 2600 20 10 x 38 12 x 30 14 x 26 16 x 22 18 x 19 18 5 x 18 5 24 2600 2900 22 12 x 36 14 x 30 16 x 26 18 x 23 20 x 20 24 2900 3400 22 12 x 36 14 x 30 16 x 26 18 x 23 20 x 20 26 3400 3600 24 14 x 38 16 x 32 18 x...

Page 32: ... etc In our system direct connection to the stat could put loads on the stat which would shorten it s life With the 24v signal we send only a few milli amps of current are required 2 It is impossible to for the installer to short anything during the installation of the thermostat Crossed connections some erratic manner but would not damage the controller board The BCB has all the time delay functi...

Page 33: ...s RS232 Communication Port Activates loop 1 through 5 Cooling loop solenoids Soaker Hose E Emergency Heat O Reversing Valve G Blower Y Compressor R 24v Hot C Common 24vAC Low Pres Ctrl High Pres Ctrl Short Pins to Reset Selects the No of loops that The board controls 2 5 High Pres Lockout LED Low Pres Lockout LED Working Properly LED Loop Switch Activating LED Diagram A 1 ...

Page 34: ...puts of the controller board are optically coupled to solid state switches so that the worst malfunction in wiring etc would produce only minor damage if at all to the output section of the control board There are 12 output connections at the bottom of the BCB located on 2 two 6 terminal connectors Terminal designa tions are as follows Left to Right Left Block 1 Cooling Loop 1 2 Cooling Loop 2 3 C...

Page 35: ... OPEN liquid line solenoid and 1 ground loop will activate followed by the blower If the system has been in the HEAT mode there will be a delay as the MODE switch timer keeps the compressor OFF for 5 minutes adjustable The compressor will start and be gin to cool using only 1 of the possible loops available MODE 1 The controller board keeps track of the actual run time hours and stores this inform...

Page 36: ...36 2005 Boreal Geothermal Inc www boreal geothermal com ...

Page 37: ...llation Data Sheet have it endorsed by the owner and return it to MANUFACTURER within 21 days after the installation of the unit 3 It is the responsibility of the building or general contractor to supply temporary heat to the structure prior to occupancy These heat pumps are designed to provide heat only to the completely finished and insulated structure Start up of the unit shall not be scheduled...

Reviews: