4.4
Installation of the battery storage system
Installation steps
Proceed as follows to install the battery storage system:
Step
Description
1
Unpack the battery storage system carefully and check it for transport damage.
In case of transport damage, contact the forwarding agent or the manufacturer immediately.
Do not use a knife to open the packing.
Never
install and operate a defective energy storage unit
2
Check whether all structural parts and accessories exist.
3
Check whether the battery storage system has been switched off.
Both LEDs must not light up.
Use a voltmeter to measure the DC voltage.
4
Bring the battery storage system on the pallet to the installation place using suitable transport aids.
5
Check whether the current isolator (NH isolator) is pulled.
Figure 4-3: representation of the pulled current isolator
The current isolator must be pulled before installation.