Environmental Requirements 

 

Please run your server in accordance with the following requirements 
1.

 

Basic Environmental Requirements: 

1.1.

 

Climatic Conditions: 

 

Description 

Requirement 

Operating Temperature 

-20-50

 

Operating Humidity 

20-90%RH (non-condensing) 

Storage Temperature 

-20-70

 

Storage Humidity 

5-95%RH

non-condensing

 

Altitude 

<2000m 

 

1.2.

 

Site Requirements of the Server Running Room: 

Please keep the server running room away from industrial pollution sources: 
For heavy pollution sources such as smelters and coal mines, the distance should be more than 5km. 
For moderate pollution sources such as chemical industries, rubber and electroplating industries, the distance should be more than 

3.7km. 

For light pollution sources such as food factories and leather processing factories, the distance should be more than 2km. 
If unavoidable, the site should be chosen in the perennial upwind direction of the pollution source. 
Please do not set your location within 3.7km from the seaside or the salt lake. If unavoidable, it should be built as airtight as 
possible, equipped with air conditioning for cooling. 

1.3.

 

Electromagnetic Environmental Conditions: 

Please keep your site away from transformers, high-voltage cables, transmission lines and high-current equipment, for example, 

there should be no high-power AC transformers (>10KA) within 20 meters, and no high-voltage power lines within 50 meters. 

Please keep your site away from high-power radio transmitters, for example, there should be no high-power radio transmitters 

(>1500W) within 100 meters. 

2.

 

Other Environmental Requirements

 

The server running room shall be free of explosive, conductive, magnetically conductive and corrosive dust. The requirements of 

mechanical active substances are shown below: 

2.1

 

Requirements of Mechanical Active Substances 

 

 

Mechanical Active Substance 

Requirement 

Sand 

<= 30mg/m

3

 

Dust (suspended) 

<= 0.2mg/m

3

 

Dust (deposited) 

<=1.5mg/m

2

 

 

 

Summary of Contents for ANTMINER S19 Pro

Page 1: ...their products and applications using Bitmain components To minimize the risks associated with customer products and applications customers should provide adequate design and operating safeguards Bitmain does not warrant or represent that any license either express or implied is granted under any Bitmain patent right copyright or other Bitmain intellectual property right relating to any combinatio...

Page 2: ...of Bitmain Information in this document is subject to change without notice and does not represent a commitment on the part of Bitmain Although the information in this document has been carefully reviewed Bitmain does not warrant it to be free of errors or omissions Bitmain reserves the right to make corrections updates revisions or changes to the information in this document Bitmain Tel 86 400 89...

Page 3: ... 1 2 Specifications 7 2 Setting Up the Server 9 3 Configuring the Server 11 4 Monitoring Your Server 12 5 Administering Your Server 13 5 1 Checking Your Firmware Version 13 5 2 Upgrading Your System 13 5 3 Modifying Your Password 14 5 4 Restoring Initial Settings 14 Environmental Requirements 15 Regulations 17 ...

Page 4: ...y screws and cables tied on the product 3 Please note that the actual server shall prevail 4 There must be an external specific Surge Protection device complying with IEC EN 61643 11 either in front of the power supply or outside the end system in a separate distribution box or as part of the building installation 5 Do not plug or remove the device when it is powered on 6 The external of the power...

Page 5: ...S19 Pro Hydro Server Installation Guide 5 1 Overview 1 1 S19 Pro Hydro Server Components The main components and controller front panel of S19 Pro Hydro servers are shown in the following figure ...

Page 6: ...S19 Pro Hydro Server Installation Guide 6 Note Power supply APW11 is part of S19 Pro Hydro server For detailed parameters please refer to the specifications below 1 Overview APW11 Power Supply ...

Page 7: ...r supply AC input voltage Volt 2 1 342 418 Power supply AC Input Frequency Range Hz 47 63 Power supply AC Input current Amp 2 2 30 Hardware Configuration Network connection mode RJ45 Ethernet 10 100M Server Size Length Width Height w o package mm 410 196 209 Server Size Length Width Height with package mm 570 316 430 Net weight kg 15 2 Gross weight kg 17 5 Environment Requirements Operation temper...

Page 8: ...r Installation Guide 8 1 Overview Notes 1 1 Inlet water temperature 2 1 Caution Wrong input voltage may probably cause server damaged 2 2 Three phase AC input 10A per wire 2 3 Operation altitude is recommended below 2000m ...

Page 9: ...the Server To set up the server 1 Go to the following site https shop bitmain com support htm pid 00720160906053730999PVD2K0vz0693 2 Download the following file IPReporter zip 3 Extract the file 4 Right click IPReporter exe and run it as Administrator 5 Select one of the following options Shelf Step Position suitable for farm servers to mark the location of the servers Default suitable for home se...

Page 10: ...a window on your computer screen 8 In your web browser enter the IP address provided 9 Proceed to login using root for both the username and password 10 In the Protocol section you can assign a Static IP address optional 11 Enter the IP address Subnet mask gateway and DNS Server 12 Click Save 13 Click https support bitmain com hc en us articles 360018950053 to learn more about gateway and DNS Serv...

Page 11: ...escription Mining address Enter the address of your desired pool The S19 Pro Hydro servers can be set up with three mining pools with decreasing priority from the first pool pool 1 to the third pool pool 3 The pools with low priority will only be used if all higher priority pools are offline Name Your worker ID on the selected pool Password optional The password for your selected worker 3 Click Sa...

Page 12: ...Server To check the operating status of your server taking S19 Pro Hydro 162T as an example 1 Click the status below to check the server status 2 Monitor your server according to the descriptions in the following table Option Description ASIC Number of chips detected in the chain Frequency ASIC frequency setting GH S RT Hash rate of each hash board GH s Temp PCB Temperature of each hash board C Ap...

Page 13: ...ministering Your Server 5 Administering Your Server 5 1 Checking Your Firmware Version To check your firmware version 1 Enter the backstage of your server find the firmware version on the bottom 2 File System Version displays the date of the firmware your server use In the example below the server is using firmware version 20210517 5 2 Upgrading Your System To upgrade the server s firmware 1 In Sy...

Page 14: ...ying you if the S19 Pro Hydro firmware can be upgraded and if yes will then proceed to flash the image 4 When the upgrade is completed the following message appears 5 Click one of the following options Reboot to restart the server with the new firmware Go Back to continue mining with the current firmware The server will load the new firmware next time it is restarted 5 3 Modifying Your Password To...

Page 15: ...oidable the site should be chosen in the perennial upwind direction of the pollution source Please do not set your location within 3 7km from the seaside or the salt lake If unavoidable it should be built as airtight as possible equipped with air conditioning for cooling 1 3 Electromagnetic Environmental Conditions Please keep your site away from transformers high voltage cables transmission lines...

Page 16: ...Requirements of Corrosive Gas Corrosive Gas Unit Concentration H2S ppb 3 SO2 ppb 10 Cl2 ppb 1 NO2 ppb 50 HF ppb 1 NH3 ppb 500 O3 ppb 2 Note ppb part per billion refers to the unit of concentration 1ppb stands for the volume ratio of part per billion ...

Page 17: ...rence in which case the user will be required to correct the interference at his own expense EU WEEE Disposal of Waste Equipment by Users in Private Household in the European Union This symbol on the product or on its packaging indicates that this product must not be disposed of with your other household waste Instead it is your responsibility to dispose of your waste equipment by handling it over...

Reviews: