BestCode Next Series 8 Technical Manual
October 2022
Page 17 of 290
Commissioning
The commissioning process is a 90-120 minute step by step guide for installing and preparing the Next Series 8 CIJ for
production operation. A video guide is available here:
Make sure the Next Series 8 Controller is properly mounted. See
for instructions.
WARNING
EQUIPMENT DAMAGE:
is completed.
Pre-fluid test
Procedure Time: 5 Minutes
1.
Navigate to the fluidic screen
Home > Service > Fluidic
2.
Press each valve button one at a time
and listen for the click.
Note: Valve 1
–
Printhead will click
when activated and de-activated since it
is a 3 way. Listen for a Click-Clack when
cycling the valve on and off.
Valve Troubleshooting
Commission the Ink Type
Procedure Time: 5 minutes
1.
Navigate to the SmartFill Technician
Screen
Login as Technician
>Service>Tools>Technician>Smartfill
2.
Select the ink type that matches the ink
to be installed and save
3.
Press the Commission System button to
Save
4.
Check the Help Screen to confirm
Summary of Contents for Next 8 Series
Page 2: ......
Page 3: ......
Page 4: ......
Page 143: ...BestCode Next Series 8 Technical Manual October 2022 Page 129 of 290 USB ...
Page 144: ...BestCode Next Series 8 Technical Manual October 2022 Page 130 of 290 Collector Information ...
Page 259: ...BestCode Next Series 8 Technical Manual October 2022 Page 245 of 290 ...
Page 264: ...BestCode Next Series 8 Technical Manual October 2022 Page 250 of 290 ...
Page 268: ...BestCode Next Series 8 Technical Manual October 2022 Page 254 of 290 ...
Page 276: ...BestCode Next Series 8 Technical Manual October 2022 Page 262 of 290 Using the Molex Crimper ...
Page 277: ...BestCode Next Series 8 Technical Manual October 2022 Page 263 of 290 ...