Commissioning
Commissioning
iso1685DP_D00272_03_M_XXEN/08.2017
24
6.5 Commissioning EDS (only iso1685DP)
Proceed as follows to put into operation an EDS after commissioning the ISOMETER®:
1.
Set the mode for the insulation fault location to manual, automatic or 1 cycle. For a
description of the different modes, refer to
.
2.
Test if the maximum locating current to the EDS is correct and adjust if necessary
(refer to
6.3.7 “Set the EDS current(only iso1685DP)” auf Seite 23
Menu path: Menu/EDS/Current
In addition to this chapter, commissioning of the ISOMETER® in combination with an EDS
is described in the
“Commissioning flow chart insulation faullt location (only iso1685DP)”
.
lle
Mode
o off
o
manually
•
auto
o
1cycle
6.6.8
lle
Current
6.6.9
o 1mA
o 1.5mA
o 2.5mA
o 3mA
o 10mA