insta-KLEEN
™ MANUAL
1MANUL334
Belanger, Inc. * PO BOX 5470 * Northville, MI 48167-5470 * Ph (248) 349-7010 * Fax (248) 380-9681
17
Installation
Getting Started
If you ordered and received the optional Conveyor, see the
Conveyor component manual for proper layout and installation.
Note:
Guide Rails are used as a reference for installing the remaining equipment. Accurate
placement of the Guide Rails is required for proper positioning of all other equipment on
the insta-KLEEN™ system.
Locate the Following Items
Guide Rail entra
nce sections, 60”
(1.524m)
2
Guide Rail c
enter sections, 60”
(1.524m)
(Quantity will vary according to options purchased)
-
Yellow Guide Plastic
(Quantity will vary according to options purchased)
10ft. (3.048m)
Accessory Box
(Content quantities will vary according to options purchased)
3/8-16 x 1-
1/4” button head bolts
-
3/8-16 lock-nuts
-
1/2 x 3-
3/4”
quick lags
-
Measure the door opening at the entrance and the exit of the building. Mark the floor at the
center points of each door. Run a chalk line the length of the tunnel from the center point of the
entrance to the center point of the exit and snap it to create the centerline of the tunnel. This will
be your reference for installing the Guide Rail.
Overhead View of Building
En
tr
a
n
ce
Exit
Place a chalk line down the center of the tunnel
Center chalk line
Summary of Contents for insta-KLEEN
Page 1: ...insta KLEEN System 1MANUAL334 Rev08 insta KLEEN System ...
Page 2: ...1MANUL334 REV 07 ...
Page 4: ......
Page 6: ......
Page 86: ......
Page 87: ......
Page 88: ......