4. Initial commissioning
4.1
Unpack the MT 601 D
1. Remove the steel band and fasteners.
2.
Carefully lift off the packaging.
3.
Remove the accessories and packaging material
from the packaging unit.
i
Check that the MT 601 D and the accessories are in
proper working order and that there are no visi-
ble signs of component damage. In case of doubt,
do not commission the unit and consult customer
service.
i
Dispose of the packaging material at an appropriate
collection site.
4.2
Setting up the MT 601 D
1.
Unfasten locating screw on MT 601 D.
2.
Attach hoisting strap as shown in illustration. The
hoisting strap must be at least the same length, and
must have enough load-bearing capacity (at least
100 kg).
Fig. 3:
Lifting the wheel balancer
Warning of damage or wrong lifting gear
Risk of injury if MT 601 D falls.
¶
Please check hoisting strap before
attaching it.
¶
Secure the hoisting strap.
¶
Lift the
MT 601 D
carefully.
3.
MT 601 D must never be lifted by the flange shaft.
After lifting, set down at prepared installation lo-
cation and pay attention to the minimum specified
distance.
Fig. 4:
Wheel balancer installation location
i
For safety reasons, the installation location must be
500 mm away from the wall.
4. MT 601 D must be secured to the ground with ex-
pansion bolts. Measuring errors will occur if it is not
fixed firmly.
4.3
Fitting the wheel-guard hood
1.
Remove nut from support bracket on the 2 wheel-
guard hoods, then remove the support bracket.
Fig. 5:
Unfastening the guard hood