Installation and Technical Information
BEGA
Replacement Parts
In the interest of product improvement, BEGA reserves the right to make technical changes without notice.
BEGA
1000 Bega Way, Carpinteria, CA 93013 (805)684-0533 Fax (805)566-9474 www.bega-us.com © Copyright BEGA-US 2018
Accessories
Please refer to the appropriate
accessory installation sheet for
further instruction when applicable.
Bega-US Architectural Lighting Fixtures and Products
http://www.bega-us.com/groupimages.aspx?imagetype=gr&groupid=253&itemnoid=
[9/28/2009 4:00:56 PM]
Linear element - LED square
84 065
Tools Required:
4mm hex key
8mm hex key
Special tool (provided)
Protection Class:
IP65
Weight:
127.9 lbs.
Dimensions
A:
8-5/8” x 8-5/8”
B:
128 ”
C:
177 ”
Relamping/Maintenance
Loosen hex socket head screws near lens and
remove top.
Clean luminaire and lens using only
solvent-free cleansers. Replace reflector and ballast
assembly and replace top. Tighten screws evenly,
making sure gasket is seated properly.
Lamp:
39.5 W LED
84 065
3/12/2018
Page 1 of 2
Description
Lens (consult factory)
Special tool - access door
LED driver (120V-277V)
LED module (4000K)
LED module (3000K)
Part No
11318710
560091
75985-03
LED-0808/840
LED-0808/830
Anchorage Kit - included
79 801
Notice to Installer for 84 065:
1. See page 2 for specific product safety warnings.
2. 79 801 anchorage kit must be installed in concrete foundation.
3. Anchorage kit 79 801 is buried below finished grade. Attention to alignment, leveling, and
location is required for proper installation.
4. LED module and LED driver provided, integral in luminaire.
79 801 anchorage installation:
1. Provide means to bring supply wiring to linear element in accordance with local code.
The template has a 3-15/16” conduit hole for conduit entry. Provide adequate foundation
reinforcement for the intended load (by others).
2. Use template and anchor bolts provided to assemble anchorage kit to be set. Make sure
anchor bolts do not protrude from lower concrete foundation more than 3” as shown.
3. Please refer to figure to establish location of lower concrete foundation. The anchorage
kit MUST BE buried. The top of the lower concrete foundation MUST be 6-7/8” BELOW
finished grade for proper installation. Position anchorage and level template properly.
4. Align and level anchorage kit so the corners of the square template are aligned with the
desired location and orientation of the corners of the square linear element. See figure.
5. Install anchorage kit using either method:
A. Attach template to forming and level properly.
B. Insert anchorage kit into poured concrete. Concrete must be vibrated to ensure
proper anchorage setting. Level template properly.
84 065 installation:
1. Once the anchorage is set, remove template and hardware.
2. Pull supply wiring to a length where splices can be seen and made through the access
door.
3. Route supply wiring through the mounting base and install mounting base using hardware
provided. Complete finished grade. See figure.
4. Use special tool provided to unlock the access door lock and remove access door. Route
the luminaire wiring down and out the hand hold for connections to be made later.
5. Loosen (8) M10 set screws at the base of the light element and place the light element
over the mounting base. Tighten (8) M10 set screws to secure to base.
6. Make supply wiring and luminaire wiring connections inside the luminaire:
MAIN VOLTAGE SUPPLY WIRE TO BLACK LUMINAIRE WIRE
NEUTRAL (COMMON) SUPPLY WIRE TO WHITE LUMINAIRE WIRE
GREEN GROUND WIRE TO GREEN LUMINAIRE WIRE
7. Replace access door and lock.