C
C.2
Installation checklist
Seria
l no.
Requirement
Fulfilled
Remarks
Yes
No
2
Installation
2.1
Has it been ensured that there are no short
circuits from the wiring of the input and out-
put terminals?
2.2
Has it been ensured that the safety switch
devices have not been bypassed as a result
of wiring errors?
2.3
Has a wiring inspection in accordance with
the installation plan been conducted
2.4
Are all connection plugs labelled according
to their allocation?
2.5
Are the connection terminals loaded with
the specified clamping torque?
2.6
Has it been ensured that the insulation of
the lines is not causing any faulty contacts?
2.7
Has the reliability of all terminal connections
been tested through mechanical tensile
loading?
2.8
Has a visual inspection of the installed com-
ponents been conducted?
2.9
Have the required installation spacings to
other components been complied with?
2.10
Do the components meet the environmental
conditions prevailing in the application?
2.11
Does the system fulfil the required type of
protection?
2.12
Is degree of pollution 2 complied with?
2.13
Is the system protected against corrosive
substances?