7.9 Install the ILite truss beam upon ILite rental tiles
The procedure below is illustrated with an ILite triple truss beam. Nevertheless, the same procedure is appli-
cable for an ILite dual truss beam.
Necessary tools
•
Hoisting equipment.
•
ILite rental truss beams.
How to install the truss beam upon rental tiles ?
1. Connect the hoist eyebolt of the truss beam with the crane of the truss installation.
Warning:
Ensure that the truss installation is able to support the complete load of the ILite rental display, which you want to set
up.
2. Place three rental tiles, in case of using a triple truss beam, or two rental tiles, in case of using a dual truss beam, next to each
other underneath the truss installation.
Caution:
Ensure that the surface where on the rental tiles will be placed is flat and clean.
Image 7-31
3. Secure the rental tiles sideways with each other by rotating the handle of the side locking mechanism 360º clockwise.
Caution:
Never use adverse force to lock the mechanism.
360º
Image 7-32
4. Place all safety clamps (A), latches (B) and row levers (C) of the rental tiles in open position as illustrated.
R5976189 ILITE RENTAL DISPLAY 16/09/2005
57
Summary of Contents for ILite
Page 1: ...ILite rental display Installation manual R5976189 04 16 09 2005...
Page 4: ......
Page 12: ...1 Safety 8 R5976189 ILITE RENTAL DISPLAY 16 09 2005...
Page 16: ...2 Installation requirements 12 R5976189 ILITE RENTAL DISPLAY 16 09 2005...
Page 34: ...5 ILite rental peripherals and accessories 30 R5976189 ILITE RENTAL DISPLAY 16 09 2005...
Page 40: ...6 Setup process of an ILite rental display 36 R5976189 ILITE RENTAL DISPLAY 16 09 2005...
Page 70: ...7 Basic setup procedures 66 R5976189 ILITE RENTAL DISPLAY 16 09 2005...
Page 76: ...8 Cabling of an ILite display 72 R5976189 ILITE RENTAL DISPLAY 16 09 2005...
Page 90: ...10 Servicing 86 R5976189 ILITE RENTAL DISPLAY 16 09 2005...
Page 106: ...B Specifications 102 R5976189 ILITE RENTAL DISPLAY 16 09 2005...