Figure 4-47 Setting Timing Command List
Chapter 5 Startup, Shutdown, and Maintenance
5.1 Startup Sequence
1)
Start the distribution box for the LED display.
2)
Start the control computer.
3)
Start the video processor.
4)
Start the sending box.
5.2 Shutdown Sequence
1)
Shut down the video processor.
2)
Shut down the sending box.
3)
Shut down the control PC.
4)
Shut down the distribution box for the LED display.