8. Do a check on the ignition of the burners
a) Make sure the ceramic logs are in the correct position as described above.
b) Make sure the plug is in the wall socket.
c) Make sure the main gas valve is open.
d) Start the appliance and do a check on the ignition of the pilot burner and main
burners. Refer to the user manual for the start procedure.
e) If the ignition of the pilot burner and main burners is correct, stop the appliance
with the remote control. Refer to the user manual for the stop procedure.
f)
Continue with the installation after the appliance has cooled down.
9. Apply the fire glass equally on the grate. Use the fire glass 'Black' along the edges of
the grate. Cover the rest of the grate with a mixture of fire glass 'Black' and fire glass
'Dark Amber' .
10. Put ceramic logs no. 36, 44, 46 and 47 on the fire glass as shown on the picture.
Figure 38.
11. Install the glass panes. Refer to chapter
for the correct procedure.
5.3.4
Do a final check on the fireplace
Safety conditions
Caution:
Wait 4 weeks after the installation before you use the fireplace. The cement
needs to harden. A final check on the fireplace can be done directly after the
installation.
Procedure
1. Start the appliance and do a check on the ignition of the pilot light and main burner.
The ignition must be quiet and must produce a calm flame. To start the appliance,
refer to the user manual.
2. Do a check on the main burner. The flames increase in height and change from blue/
yellow to yellow.
3. If all flames are yellow, the appliance is ready for use.
Installation
Gas Fire Panorama 70-55
47
Summary of Contents for 70-55 PF2
Page 1: ...Installation and maintenance manual Gas Fire Panorama 70 55 PF2 Serial number Production date...
Page 50: ...2 Remove the side panels and front panel Maintenance 50 Gas Fire Panorama 70 55...
Page 71: ...9 3 Gas Fire Panorama 70 55 PF2 with 4 cm frame Dimensions Gas Fire Panorama 70 55 71...
Page 73: ...9 5 Gas Fire Panorama 70 55 PF2 with 6 cm frame Dimensions Gas Fire Panorama 70 55 73...
Page 75: ...9 7 Gas Fire Panorama 70 55 PF2 with 10 cm frame Dimensions Gas Fire Panorama 70 55 75...
Page 78: ...9 10 Operating unit Dimensions 78 Gas Fire Panorama 70 55...
Page 81: ...11 EU Declaration of Conformity EU Declaration of Conformity Gas Fire Panorama 70 55 81...
Page 82: ...EU Declaration of Conformity 82 Gas Fire Panorama 70 55...
Page 83: ...EU Declaration of Conformity Gas Fire Panorama 70 55 83...