background image

 

Disconnect the con::cube from power supply and open the cover to the terminal compartment.

 

Connect the black wire of the pump to 

GND

 of the 12 V power supply of the con::cube  (black terminals at 

the cottom of the con::cube).

 

Connect the red wire of the pump to the input of the digital relay (e.g. 

45 Relay 1 NO

).

 

Connect the 12 V power supply of the con::cube (red terminals at the bottom of the con::cube) with a cable 

bridge to the other input (e.g. 

46 Relay 1 C

) of the used digital relay.

 

Check if the pump is set to step 3 to ensure the correct power consumption (see section 9.8).

 

Reconnect the con::cube to the power supply and wait until moni::tool has started up.

!

The pump must not run dry.

micro::station / nano::station, 03-2023 Release

www.s-can.at

Copyright © s::can GmbH

25 / 36

Summary of Contents for scan micro station

Page 1: ...Manual micro station nano station March 2023 Release S 36 M...

Page 2: ......

Page 3: ...45 ALARM 18 5 2 1 Connection of flow detector F 45 ALARM to con lyte D 320 18 5 2 2 Connection of flow detector F 45 ALARM to con cube 19 5 3 Connection of Pressure Sensor F 500 P 21 5 3 1 Connection...

Page 4: ...3 Process Connection 30 9 4 Flow Detector 30 9 5 Inlet Strainer 31 9 6 Flow Restrictor 31 9 7 Pressure Sensor 32 9 8 Water Pump 32 9 9 Service Set 33 10 Technical Specifications 34 micro station nano...

Page 5: ...an by s can This original manual serves as the reference in case discrepancies occur in versions of the manual after translation into third languages This manual and all information and figures contai...

Page 6: ...self the local legislation and requirements e g regarding electrical connection are observed All s can products are leaving our factory in immaculate technical and safety conditions Inappropriate or n...

Page 7: ...d a flow restrictor ensures correct pressure and discharge A flow detector alarms when the flow is too low The water leaves the station pressure free free atmosphere With the help of a shut off valve...

Page 8: ...NANO 8 8 parameters Turbidity TOC UV254 color EC pH 2 disinfection parameters alarm mounted on panel with flow cell autobrush flow detector and con cube operator terminal event detection software incl...

Page 9: ...s can stations has been optimized Modified dimensions or similar are marked with the note version since 2023 micro station waster water figure on the right micro station nano station 03 2023 Release w...

Page 10: ...g valve Flow detector digital Process concection Inlet strainer Flow cells for waste water Pressure sensor analog i scan Flow restrictor Flow cell for i scan with autobrush and 2 sensors incl flow res...

Page 11: ...water in mm For the version until the end of 2022 the total width of the panel is 450 mm The inlet is 135 mm and the outlet 290 mm from the left edge micro station nano station 03 2023 Release www s...

Page 12: ...Dimensions of micro station waste water in mm micro station nano station 03 2023 Release Copyright s can GmbH www s can at 12 36...

Page 13: ...mm For the version until the end of 2022 the vertical spacing of the mounting holes is 730 mm The outlet was via the floor outlet of the flow cell micro station nano station 03 2023 Release www s can...

Page 14: ...eated as household waste It must be disposed and recycled as electronic waste Please assist to keep our environmen 3 5 Scope of Delivery Immediately upon receipt please check the received consignment...

Page 15: ...ical specifications located at the end of this manual Infrastructure Power supply for controller for operation operational reliability voltage power peak free Correct dimensioning mounting and protect...

Page 16: ...probes and sensors are to be installed in the flow cells provided which are already mounted on the panel This is done according to the mounting instructions chapter 4 of the respective manuals of the...

Page 17: ...o the manual of the control ler for operation Check the plausibility of the readings obtained after sufficient running in time at least 15 minutes If necessary calibrate the readings of the i scan to...

Page 18: ...ght button to switch to the Status display Push the Function button Select the menu Manage sensors and confirm with OK Select the men Add sensor and confirm with OK Select the menu Add digital in and...

Page 19: ...addition create a cable bridge between 12 VDC red terminal at the bottom of the con cube and the digital input see figure on the right Reconnect the con cube to the power supply and wait until moni t...

Page 20: ...low Enter the Text for value 0 e g no flow Enter the Text for value 1 e g flow OK Push the button Save to store the configura tion 6 7 8 9 6 7 8 9 micro station nano station 03 2023 Release Copyright...

Page 21: ...h OK The successful installation is confirmed with ADDED in the top line Push the Back button to return to the menu Sensor configuration Select the menu Configure and confirm with OK Select the entry...

Page 22: ...om of the con cube with the positiv input e g 1 of the used analog input Analog In with a cable bridge Reconnect the con cube to the power supply and wait until moni tool has started up Click the Serv...

Page 23: ...number of decimal places Reso lution to 2 Set the Upper limit to 10 and the Lower limit to 0 Check if the Mode is set to 4 20mA and the Error Mode is set to Limit Push the button Save to store the se...

Page 24: ...word admin1 or your individual user name Click on the icon Outputs and click on the menu entry Digital Outputs in the new window Click on the icon Edit for the 1 digital output digitalOut1 Push the bu...

Page 25: ...relay e g 45 Relay 1 NO Connect the 12 V power supply of the con cube red terminals at the bottom of the con cube with a cable bridge to the other input e g 46 Relay 1 C of the used digital relay Che...

Page 26: ...tion itself includes the following steps see also section 8 for typical error patterns Check if any leakage is visible on the flow cells or hose connections screw fittings Check and clean the strainer...

Page 27: ...e mode on the operator terminal Close the inlet valve Unscrew the transparent cover of the inlet strainer Remove the filter sieve Clean all parts of the inlet strainer with tap water Check the filter...

Page 28: ...e waiting time after compressed air cleaning Extend discharge 8 2 Return Consignment RMA Return Material Authorization Return consignments of the s can monitoring system or parts of the system shall b...

Page 29: ...1 US Environment rating IP IP44 IP55 C 31 EU C 31 US 9 2 Inlet Valve Each monitoring station for clean water is permanently equipped with a 2 way ball valve This allows the inlet to the monitoring sta...

Page 30: ...very F 48 PROCESS F 48 fitting to G 1 Material Nylon PA PVC F 46 PROCESS F 48 PROCESS 9 4 Flow Detector To monitor the minimum flow rate a digital flow detector is installed after the inlet in the mic...

Page 31: ...at the same time protect the sensors from excessive pressure a flow restrictor is installed in the station after the optical mea surement spectrometer probe or i scan Name Specification Remark Part no...

Page 32: ...cess connection 1 4 G external thread 9 8 Water Pump Optionally the station can be equipped with a feed pump to ensure sufficient flow If the power is supplied via the con cube the power requirement o...

Page 33: ...sensor 1 piece Dummy plug for flow cell autobrush incl connecting nut je 2 pieces Safety bracket for sensor 2 pieces Mounting holder for flow cell Replacement brush for autobrush spectromer probe 2 pi...

Page 34: ...L xx F 508 PANEL per part Required space min 210 mm min 8 27 inch Installation depth Mounting 4 mounting holes 9 mm per panel Material PE HD white PP grey F xxx ECO F 506 PANEL xx F 508 PANEL Material...

Page 35: ......

Page 36: ...s can GmbH Brigittagasse 22 24 1200 Vienna Austria Tel 43 0 1 219 73 93 0 Fax 43 0 1 219 73 93 12 office s can at www s can at...

Reviews: