Tests
Page 15 / 23
MID_VD_BA_02_1607
7. Tests
7.1 Main test
The main test is the standard process for meter testing. The result of this test is
automatically stored in the memory of the Verification Device and can be downloaded
from the PC program.
The procedure is the following one:
1. Switch off the flow meter and connect the specific wire harness to the amplifier
circuit board.
2. Connect the male D-25 connector of the harness to the corresponding female
connector on the Verification Device.
3. Switch on the flow meter and be sure that the meter is not in the programming
mode when the test starts.
4. Press the “On/Off” button on the Verification Device and wait for the “SelfTest” to
complete.
5. When the Start Menu appears on the display, press the upper left function key.
6. When the Main Test option is highlighted, press the “OK” button.
7. Press the appropriate numbers on the numeric keypad for the Test ID and press
“OK”. The Test ID is a value which can be used as a customer tag.
8. Select if the detector tube is inside dry or wet. This selection has influence on the
test results of the electrode measurement.
9. The tests are now automatically carried out in 10 steps. During the test, the flow
meter shows “Testing in progress” on the display.
10. The result will be “passed” or “failed”.
11. If the test failed, press the function key on the upper left “View Report” to see the
results. See example below.