9.  Once the above has been done, please verify all the connections to ensure everything is 

as specified. 

10.  Follow the instructions as specified in the installer manual before switching the batteries ON. 

11. When ready to switch the battery ON, flip the DC break switch to the ON position. 

12. Press and release the RESET switch on each of the batteries for the BMS to switch ON as 

the batteries are shipped in its SLEEP state. 

a.  The green RUN LED will start flashing if everything is working. 

b.  Refer to Table 3 for the LED indicator description. 

13. The inverter should automatically detect the BMS settings via the CANBUS connection once 

connected. 

14. Verify  that  the  battery  is  communicating  with  the  BMS  by  checking  the  charging  and 

discharging  parameters  on  the  inverter.  The  charge  and  discharge  current  values  on  the 
inverter should match the values as in Table 5. These values should update automatically on 
the  inverter.  The  battery  voltage,  charge-and-discharge  current,  SOC  value  and  battery 
temperature  will  be  sent  through  to  the  inverter.  Please  refer  to  figure  6  for  parameters 
displayed on a SunSynk inverter with the AZBAT48100 batteries. 

 

 

Figure 6: Inverter charge and discharge information received from the battery BMS. 

The figure on the left displays the charge and discharge information for an installation using 1 battery. 
The figure on the right displays the information when 2 batteries are connected in parallel. These 
values should match that as referenced in Table 5 for the number of batteries connected in parallel. 

  Parallel connection 

When using more than one battery, the first battery will be the MASTER and the other batteries will 
be SLAVES. The CANBUS connection from the inverter will be connected to the MASTER battery. 
The  RS485 cable/s will link the parallel SLAVE batteries to the MASTER battery. The DIP switch 
(address) of the MASTER and the SLAVES need to be configured. Please refer to the following table 
for the DIP switch settings: 

 

 

 

Summary of Contents for AZBAT48100B

Page 1: ...g instructions in this document before operating the battery Table of Contents LITHIUM IRON PHOSPHATE BATTERY 1 AZBAT48100B 1 PRODUCT MANUAL 1 REVISION HISTORY 2 DISCLAIMER 2 OVERVIEW 2 PRODUCT INFORM...

Page 2: ...48100B incorporates 30x 3 2V 15S2P configuration 50Ah Lithium Iron Phosphate LiFePO4 cells with a 1C charge and discharge rating The battery incorporates a battery management system BMS which provides...

Page 3: ...teq Pty Ltd 2021 AZBAT48100B Product Manual Page 3 of 17 All Rights Reserved Revision 1 00 February 2021 Azoteq PowerSense Series Product Information Production dimensions Figure 1 AZBAT48100B physica...

Page 4: ...arge Voltage 54 8V Float Sustain Voltage 54V Standard Charge 30A 0 3C Maximum Charge 50A 0 5C BMS protection for higher charge current Standard discharge 50A 0 5C Maximum Discharge 95A 0 95C BMS Commu...

Page 5: ...erature recovery 15 C Environmental over temperature protection 70 C Environmental temperature recovery 60 C Environmental under temperature 20 C Environmental under temperature recovery 15 C Power ov...

Page 6: ...ned on initially Please refer to Table 3 for the LED indicator definitions Switching ON This is done with a short press and release of the switch after which the green RUN LED will start to flicker gr...

Page 7: ...SOC DESCRIPTION GREEN RED GREEN GREEN GREEN GREEN SHUT DOWN SLEEP OFF OFF OFF OFF OFF OFF ALL OFF STANDBY NORMAL FLASH 1 OFF OFF OFF OFF OFF STANDBY STATUS CHARGE NORMAL ON OFF BASED ON CAPACITY HIGH...

Page 8: ...port definitions The battery has a two RJ45 MODBUS RS485 communication ports and one RJ45 CANBUS port Please refer to the tables below for the port definitions Figure 4 RJ45 network cable pin referen...

Page 9: ...s 2 CANBUS communication cable usually supplied with the inverter 3 Parallel communication cable when using multiple batteries 4 Ground cable and screw M5 to earth the battery to the installation 5 DC...

Page 10: ...e the polarity of the connection between the inverter and the batteries are correct 6 Connect the RS485 cables between the batteries when using multiple batteries a As depicted by the yellow connectio...

Page 11: ...es on the inverter should match the values as in Table 5 These values should update automatically on the inverter The battery voltage charge and discharge current SOC value and battery temperature wil...

Page 12: ...ghts Reserved Revision 1 00 February 2021 Azoteq PowerSense Series Table 5 Address DIP switch configuration OF BATTERIES ADDRESS SETTING CHARGE CURRENT DISCHARGE CURRENT 1 MASTER 45A 95A 2 MASTER 55A...

Page 13: ...on top of each other when using multiple batteries in parallel Each battery should be installed on a mounting plate to allow air circulation Please refer to Appendix A for an expanded list of address...

Page 14: ...e inverter is not powered from AC mains while connecting the battery 6 It is advised to use suitable protection between the battery and the inverter 7 Make sure the polarity positive and negative conn...

Page 15: ...the material safety datasheet MSDS for the batteries on the Azoteq website Leaking cells 1 In the event of a cell leaking liquid or gas take caution to prevent any contact with the skin and eyes and i...

Page 16: ...Copyright Azoteq Pty Ltd 2021 AZBAT48100B Product Manual Page 16 of 17 All Rights Reserved Revision 1 00 February 2021 Azoteq PowerSense Series Appendix A Expanded DIP Settings...

Page 17: ...for any purpose Azoteq disclaims all warranties and conditions with regard to these products and information including but not limited to all implied warranties and conditions of merchantability fitne...

Reviews: