To check a schedule
1
If the TimeLiner window is not already open, click Tools
➤
TimeLiner.
2
In the TimeLiner window, the Tasks tab, right-click the tasks view, and click Check.
3
Select one of the available options:
■
Find uncontained items. Choose this to select any items in the scene that are not attached to a task, or
are not contained within any other item attached to a task.
NOTE
A Contained item is the child of another item. For example, if you select a Group, Block or Cell which
is comprised of various pieces of geometry, then that geometry is
contained
within the Group, Block or Cell.
A Group, Block or Cell may therefore be
attached
to a task and although the child geometry is not directly
attached itself, it is
contained
within an item that is attached.
■
Find contained items. Choose this to select any items in the scene that are either attached to a task or
contained within any other items attached to a task.
■
Find attached items. Choose this to select any items in the scene that are directly attached to a task.
■
Find items attached to multiple tasks. Choose this to select any items in the scene that are directly
attached to more than one task.
■
Find items contained in multiple tasks. Choose this to select any items in the scene that are either
attached to, or contained within any other item that is attached to more than one task.
■
Find items attached to overlapping tasks. Choose this to select any items in the scene that are attached
to more than one task, where the task durations overlap.
■
Find items contained in overlapping tasks. Choose this to select any items in the scene that are either
attached to, or contained within any other item that is attached to more than one task, where the task
durations overlap.
The check results are highlighted on the Selection Tree and in the Scene Area.
Link to External Project Files
One of TimeLiner most powerful features is its integration with project scheduling software. A list of tasks
including their start and end dates/times can be imported from a project file directly into TimeLiner.
Supported Scheduling Software
Autodesk Navisworks TimeLiner supports a variety of scheduling software.
NOTE
Some of these may only function if the relevant scheduling software is installed.
360 | Chapter 15 Simulate Construction Scheduling
Summary of Contents for 507B1-90A211-1301 - NavisWorks Manage 2010
Page 1: ...Autodesk Navisworks Manage 2010 User Guide March 2009 ...
Page 12: ...xii Contents ...
Page 14: ...2 Part 1 Welcome to Autodesk Navisworks Manage 2010 ...
Page 64: ...52 Chapter 3 Installation ...
Page 97: ...Get a Whole Project View 85 ...
Page 98: ...86 Part 2 Get a Whole Project View ...
Page 136: ...124 Chapter 5 Work with Files ...
Page 178: ...To toggle ViewCube Click View Head Up Display ViewCube 166 Chapter 6 Explore Your Model ...
Page 262: ...250 Chapter 9 Use Viewpoints and Sectioning Modes ...
Page 270: ...258 Chapter 11 Work Within a Team ...
Page 282: ...270 Chapter 12 Share Data ...
Page 346: ...334 Chapter 14 Create Photorealistic Visualizations ...
Page 460: ...448 Chapter 17 Autodesk Navisworks Reference ...
Page 466: ...454 Glossary ...