SuperTrak™ GEN3 System Operation and Maintenance Manual
47
Rev. 9 (12-2021)
Installation
This section describes how to install the SuperTrak conveyance platform.
Prerequisites
The following services and components are required to successfully install the
SuperTrak conveyance platform:
•
A non-compressing installation surface (for example; a concrete floor)
•
Electrical connections to the SuperTrak conveyance platform control panel:
•
AC incoming power from the main electrical cabinet
•
North America: PE, 40A (or 20-30A on smaller
systems)
•
Europe: PE, 40A (or 20-30A on smaller systems)
•
Safety circuit connection (fail safe digital 24V output to enable motor
power)
•
PLC network connections (EtherNet/IP, PROFINET, or alternate)
•
TrakMaster software
•
Computer with Windows and network connectivity
•
Ethernet cable
•
Tools:
•
0.5 mm (0.02 in.) shims
•
Feeler gages
•
Framing square
•
Mallet
•
Straight flat bar 38.5 cm (15.16 in.) long
•
Precision spirit level
•
Set of metric hex keys
•
Set of metric wrenches or spanners
Summary of Contents for SuperTrak GEN3
Page 1: ...Rev 9 December 2021...
Page 2: ......
Page 3: ...SuperTrak GEN3 Conveyance Platform Modular Conveyor Operation and Maintenance Manual...
Page 6: ......
Page 12: ...This page is intentionally blank...
Page 30: ...This page is intentionally blank...
Page 58: ...This page is intentionally blank...
Page 296: ...This page is intentionally blank...
Page 300: ...This page is intentionally blank...
Page 364: ...This page is intentionally blank...
Page 366: ...This page is intentionally blank...