1.  The inverters has triple MPPTs. For MPPT1, users can connect two strings. For MPPT2 and 

MPPT3, users can connect one string.

Step 1: Strip 1/4-5/16inch(6-8mm) insulation from the cable end and crimp OT rings for the cable ends.

Step 3: Secure the conduit fitting to the enclosure using the counter nut.

2.  When users connect 2 strings to MPPT1, make sure the two strings has same quantity of 

solar panels. The inverter will limit the total MPPT1/MPPT2/MPPT3 input current to 

25A/15A/15A automatically. 

3. The inverter will limit the max solar input power to 18kW totally.

09

10

face the same direction

Steps for PV connection

d. Route the PV conductors through the 

conduit and conduit fitting into the inverter.

a.  Strip off 1/4-5/16inch(6~8mm) insulation 

on the PV string positive and negative 

conductors.

b. Use wire ferrules for PV string conductors 

if they are stranded wire type.

c. Insert the conduit fitting to the opening 

for PV connection and tighten it from inside 

using the counter nut.

e. Secure the cable gland in place.

f. Ensure that the cables are connected 

correctly and securely. Then take appropriate 

measures to ensure that the conduit and conduit 

fittings are fastened reliably, and seal the cable 

entry holes.

3.5     Battery Connection

3.5.1   Battery power cable connection

2

3/0-4/0 AWG(85-100  mm )

600V

Cable Requirement:

12K

Step 2: Route the battery power cable through the cable gland, connect positive to BAT+,negative to BAT-.

Step 5: Fix the cable gland in place. 

Step 4: Fasten the OT rings of battery positive and negative cables to the lugs according to the marking.

Polarity reverse will damage the inverter!

Install a DC isolator between battery and 

inverter can avoid potential damages 

caused by electric arc.

3.5.2    Battery communication cable connection

A correct battery communication cable must be used to connect the battery to the inverter when users 

choose lithium-ion battery type. Please select ‘Lead-acid ‘ type if the lithium battery can not communicate

 with inverter. The battery communication port on inverter is a RJ45 socket, Pin for the RJ45 plug of the 

communication cable is as below. Make the communication cable according to the below inverter Pin and 

the correct pinout of communication port on battery. The inverter supports both CAN and 

RS485 communication.

Pin

1

Description

2

3

4

NC

GND

NC

BAT CAN H

5

6

7

8

BAT RS485 A

NC

BAT RS485 B

Pin

1 2 3 4 5 6 7 8

BAT CAN L

Battery CAN&RS485

20(N.M)

Minimum Voltage

Model

Cable Size

Torque for cable connection

OT ring

RNB100-10

Summary of Contents for ATL12KW2897-22

Page 1: ...Version EN UM 1 0 00 Atlas Energy Solutions 848 W 1440 N suite 120 Logan UT 84321 1 435 233 6115...

Page 2: ...CT Meter connection 3 6 4 13 Working with Generator 3 7 15 Generator system connection 3 7 1 15 Generator Startup and stop settings 3 7 2 17 Monitor System Setup 3 10 21 3 10 1 3 10 2 Wifi GPRS 4G WLA...

Page 3: ...can interconnected with the utility grid Avoid misoperation and Inappropriate Usage All the work of this product system design installation operation setting configuration and maintenance must be car...

Page 4: ...system B AC Coupling with existed solar system C On grid solar system without battery Support EPS even without battery D Off grid and back up applications E Single and three phase paralleling system...

Page 5: ...ing bracket then drill 4 holes of 8mm 5 16inch diameter and make sure the depth of the holes is deeper than 50mm 2inch Step3 Hang the inverter onto the wall mounting bracket and lock the inverter on t...

Page 6: ...CAN RS485 please check Chapter 3 5 2 for Pin definition please check Chapter 3 9 for Parallel connection e Parallel communication port f FAN1 2 3 g TEMP Connection for temperature sensor of lead acid...

Page 7: ...duit fittings are fastened reliably and seal the cable entry holes 3 5 Battery Connection 3 5 1 Battery power cable connection 2 3 0 4 0 AWG 85 100 mm 600V Cable Requirement 12K Step 2 Route the batte...

Page 8: ...y master and slave settings 1 The temperature sensor for lead acid battery is optional If you need it please contact distributor for purchasing For Li ion battery For Lead acid battery 2 There are thr...

Page 9: ...talled at the service entry point in or near the main service panel We standard supply 2 CT for one inverter The CT interface for 2 CTs connection is a RJ45 port we have made a RJ45 plug on those 2 CT...

Page 10: ...ter Service Disconnect Generator Inverter Disconnect Generator Disconnect Backup Panel Generator Connection Whole Home Backup PE N PE L1 L2 PE N L2 L1 PE N L2 L1 2 wire start CT 2 CT 1 When generator...

Page 11: ...kw h 10A Generator Start Conditions Generator Stop Conditions when battery voltage or SOC higher than Charge end Volt SOC settings value When grid is off the hybrid inverter will work as a power sourc...

Page 12: ...erent using scenarios Up to 10 units can be paralleled to reach a capacity of 120kW Wiring diagram is as below The manual bypass switch connect loads to EPS panel for default When inverters fail users...

Page 13: ...ur mobile phone to the BAxxxxxxxx wireless network where BAxxxxxxxx is the serial number of the WiFi dongle luxpower_5G luxpowertek luxpowertek_5g HF WIFI ChinaNet EWP ChinaNet wG49 CMCC BAKR luxpower...

Page 14: ...arallel cable communication Interface DRM Interface Meter INV485 4 Operation Guide 4 1 Operation Mode The inverter has different working mode to meet customers various demands the working modes are as...

Page 15: ...2 3 1 Import Power Example 4 1 3 AC Charge Mode Users can charge battery with grid power when electricity price is cheap and discharge battery power to supply load or export to the grid when electric...

Page 16: ...m of the screen you ll see all current and historical fault warning information on this page Alarm record M8 Rx fault Inconsistant Fault status Fault record Alarm status M3 Rx failure Model fault Rese...

Page 17: ...its CT ratio is either 1000 1 or 3000 1 and set it accordingly the battery brand in the Lithium brand drop down list Meter type Please select it according to the meter that s to be installed Offgrid...

Page 18: ...ntact Luxpower service or your inverter supplier 1 Check if the L1 L2 and N wires are connected correctly at inverter EPS output port 2 Disconnect the EPS breaker to see if fault remains If fault pers...

Page 19: ...n EPS port Restart inverter If fault still exists contact Luxpower service or your inverter supplier Check if meter communication cable is connected correctly on inverter and meter side RSD Active Off...

Page 20: ...llowing up the below diagram if there is problem with the fans Turn off the system and wait for more than 5 minutes before disassembling the machine c Loosen the screws and remove them d Remove the fa...

Page 21: ...an activation the Rule21 function Setting the value in the corresponding blank Before setting you can read the default value first and then set the parameter of the function that needs to be modified...

Page 22: ...mum Adjustable Range 61 0Hz 180s 180 50 0Hz 160ms 61 8Hz 160ms Maximum Adjustable Range 59 0Hz 66 0Hz 1000s 1000s 57 0Hz 1000s 66 0Hz 1000s 6 2 4 Specified Power factor SPF Parameter name Default Valu...

Page 23: ...Q2 Q3 Constant Reactive Power 44 of nameplate apparent power Parameter name Default Value Under excited Under excited Over excited Disable Constant Reactive Power Mode Minimum Adjustable Range Under e...

Page 24: ...208V 10400 18000 250 250 25 15 15 34 17 17 100 140 100 600 120 500 360 3 2 1 1 180 270 240 0 8 0 8 leading Adjustable 60 55 65 3 35 0 99 full load 240 120 240 120 208 3 20 60 97 5 94 99 9 48 40 60 Le...