6. Operation
6.1. Pre-Operation Procedure
Each time before starting operation of the generator, perform the following
inspections. Any failure of these inspections must be addressed and corrected
before attempting to start the generator.
Step 1.
Inspect power cord for degradation, frays, prong damage, etc. Replace the
power cord if necessary. Use only the ATI-supplied power cord (See Appendix C
Spare Parts List for replacement).
Step 2.
Inspect inert gas source for proper gas type, adequate tank pressure, and
regulator operation.
Step 3.
Inspect inert gas line, checking for any leaks, cracks, kinks, or signs of wear.
Replace the line if necessary.
Step 4.
Inspect liquid aerosol reagent container label for proper identification.
Also inspect liquid aerosol reagent for cleanliness and transparency.
Step 5.
Fully close the Metering Valve and push the Aerosol Switch to OFF.
Step 6.
Place the generator in the location where it will be used. Once the
generator begins to heat up, it should not be moved.
Step 7.
Position the generator so controls are readily accessible.
Summary of Contents for 5D Thermal Aerosol Generator
Page 1: ...5D Thermal Aerosol Generator 1 5D Thermal Aerosol Generator Operator Manual www atitest com...
Page 2: ......
Page 6: ...3 2 Precautions...
Page 7: ...5D Thermal Aerosol Generator 4 Precautions Espa ol...
Page 8: ...5 Precautions Fran ais...
Page 9: ...5D Thermal Aerosol Generator 6 Precautions Svenska...
Page 10: ...7 Precautions...
Page 34: ......
Page 35: ......
Page 36: ......