Apricus AP250GLE Installation Manual Download Page 10

                          Issue Date: 01.06.16 

 

     

   Review Date: 01.06.16  

H0024 028626 A  

Installation Manual for EHW Tanks: MAN_INST_TANK_SRT(AA)|10

 

 

Figure 3 Apricus Pump Station Kit 

5.3.1.3 SOLAR RETURN 

IMPORTANT 

Cap  this  port  with  brass  plugs  supplied  when  solar 
collectors are not being installed. 

 
When solar DHW system is set up, this port is used for the 
water line returning from the solar collectors after being 
heated.  This  line  does  not  require  any  additional 
components, but should be run as short as possible and 
have continuous fall back to the solar return port. 

Apricus  recommends  using  a  three  way  ball  valve  and 
drain on the solar return line to allow convenient system 
filling and draining.  

On  the  solar  return  line  near  the  tank  port,  it  is 
recommended  to include a U-shaped heat trap  with an 
approximate  25cm  dip  in  the  piping  configuration  to 
prevent reverse thermos-siphoning. 

5.3.1.4 OUTLET 
The  outlet  is  where  the  hot  water  from  the  tank  is 
extracted to be supplied to the household.  

5.3.1.5 SENSOR PORTS 
When solar DHW system is set up, the sensors must be 
coated with heat transfer paste and inserted through the 
cable  gland  into  the  appropriate  sensor  port  and 
tightened. The top sensor port houses S3 and the bottom 
sensor port houses S2. 

The  Apricus  controller  requires  three  sensor  leads  be 
installed  into  the  appropriate  sensor  ports  in  the  solar 
system; this is vital for operation of the solar system.  

The first temperature sensor port is located on either side 
of  the  collector  manifold.  Sensor  1  (S1)  must  be 
connected to the outlet of the manifold (the higher side). 
Apricus  solar  rated  tanks  come  with  two  temperature 
sensor ports. The bottom port connects to the Sensor 2 
(S2), the top port connects to the Sensor 3 (S3) sensor. 

5.3.1.6 PTRV PORT 
The  PTRV  port  is  where  the  tank  ‘pressure  and 
temperature  relief  valve’  is  to  be  installed.  All  PTRV’s 
must  be  fitted  with  a  copper  drain  pipe  to  carry  any 
discharge to an appropriate drain. 

IMPORTANT 

All storage tanks include a PTRV, which is located  in 
the tank packaging, either in a box, vertical column or 
element cover. 

 

Summary of Contents for AP250GLE

Page 1: ...Issue Date 01 06 16 Review Date 01 06 16 H0024 028626 A Installation Manual for EHW Tanks MAN_INST_TANK_SRT AA 1 Apricus Solar Hot Water Installation Manual For Electric Hot Water Tanks Solar Ready...

Page 2: ..._SRT AA 2 CONTENTS CHAPTER 1 INTRODUCTION 3 CHAPTER 2 WARNINGS AND PRECAUTIONS 4 CHAPTER 3 SITE INSPECTION 6 CHAPTER 4 COMPONENT INSPECTION 7 CHAPTER 5 SYSTEM PLUMBING 8 CHAPTER 6 COMMISSIONING 11 CHA...

Page 3: ...d Tube functions to harness the solar energy by capturing and retaining the heat due to the presence of the vacuum Flow Line The plumbing line running from tank solar flow port to the inlet of the col...

Page 4: ...ROL Where the mains supply pressure can exceed or fluctuate beyond the pressure of 500kPa a pressure limiting valve must be fitted to the cold mains line The device is installed after the duo valve is...

Page 5: ...ery important that the auxiliary boosting system remains on It will only activate if the temperature falls below the temperatures outlined 2 5 EHW TANK 2 5 1 HYDROGEN BUILD UP Glass lined vitreous ena...

Page 6: ...For glass lined tanks consider the positioning of the tank to allow room for anode removal and replacement maintenance The storage tank must be installed in a properly drained safe tray where leakage...

Page 7: ...an electric element Ensure the tank has two brass plugs 4 2 NECESSARY COMPONENTS Ensure that the following components have been sourced for the installation These are not provided as a standard with t...

Page 8: ...ATERIAL AND PIPE SIZE For domestic installations the recommended pipe is copper and the size is Two factors affect the choice of pipe sizing the flow rate and pressure drop These two factors are close...

Page 9: ...ECV Pressure Reducing Valve Four Way Cross Figure 2 Mains Line Valves The set of mains line valves can be purchased as a kit from Apricus and provides the above components with insulating jackets to...

Page 10: ...extracted to be supplied to the household 5 3 1 5 SENSOR PORTS When solar DHW system is set up the sensors must be coated with heat transfer paste and inserted through the cable gland into the approp...

Page 11: ...er all the plumbing connections have been made EHW tank needs to be filled with water and purged of air To fill the system 1 Open the cold mains line and fill up the tank and open the hot water outlet...

Page 12: ...he electrical element will be required to be directly connected to a 240V AC 50Hz mains power supply Flexible conduit is required to enclose any exposed electrical cables to the storage unit 7 2 2 THE...

Page 13: ...us EHW tank ensure that each of the following processes is carried out prior to leaving the site 8 1 CHECKLIST PRIOR TO LEAVING INSTALLATION SITE EHW tank check Check all connections for leaks and tha...

Page 14: ...sue Date 01 06 16 Review Date 01 06 16 H0024 028626 A Installation Manual for EHW Tanks MAN_INST_TANK_SRT AA 14 CHAPTER 9 APPENDIX 7 1 3 6 5 4 2 Figure 4 Typical Electric boosted solar hot water syste...

Page 15: ...or adverse water conditions including excessive water pressure or temperature neglect of any kind or otherwise as a result of any use of the Unit contrary to the product manual or other instructions p...

Page 16: ...annot be excluded under the Australian Consumer Law You are entitled to a replacement or refund for a major failure and for compensation for any other reasonably foreseeable loss or damage You are als...

Reviews: