GASGUARD IS CONTROLLER Issue: R2, Date: 26/09/2011, CRN: 7502
Page 28
4.4.5
Set Relay Start-Up Mode
5.
To modify ‘PwrUpMode’ press the
key to enter
6.
Use the
key to toggle between LIVE and LATCHED
7.
To save, use the
key
8.
To escape, use the
key
4.5
Output Configuration Menu
To view and modify the Output Configuration settings use the following procedure. This procedure can be applied to
the configuration of all three outputs. Note: Outputs are always 4-20mA even if the inputs are 0.4-2.0V types.
1.
Once in the Configuration Main Menu, scroll down using
key to position 15 Output Configuration
2.
Press
key to enter into sub-menu
4.5.1
Set Output Status
1.
To modify ‘Status’ press the
key to enter
2.
Use the
key to toggle between ON and OFF
3.
To save, use the
key
4.
To escape, use the
key
4.5.2
Set Output Tag Name
1.
To modify ‘Output’ press the
key to enter
2.
Use the
key to scroll through the alpha-numerals
3.
Use the
key to move cursor across to the next digit
4.
To save, use the
key
5.
To escape, use the
key
4.5.3
Set Output Type
1.
To modify ‘OP Type’ press the
key to enter
2.
Use the
key to toggle between FOLLOW, HIGHEST, and LOWEST
3.
To save, use the
key
4.
To escape, use the
key
4.5.4
Set Output to Channel 1
1.
To modify ‘CH1’ press the
key to enter
2.
Use the
key toggle between IN and NOT IN
3.
To save, use the
key
4.
To escape, use the
key
4.5.5
Set Output to Channel 2
1.
To modify ‘CH2’ press the
key to enter
2.
Use the
key toggle between IN and NOT IN
3.
To save, use the
key
4.
To escape, use the
key
Summary of Contents for gasguard
Page 47: ...GASGUARD IS CONTROLLER Issue R2 Date 26 09 2011 CRN 7502 Page 46 ...
Page 62: ...GASGUARD IS CONTROLLER Issue R2 Date 26 09 2011 CRN 7502 Page 61 B2 Main Menu Flowchart ...
Page 63: ...GASGUARD IS CONTROLLER Issue R2 Date 26 09 2011 CRN 7502 Page 62 B3 Calibration Flowchart ...
Page 64: ...GASGUARD IS CONTROLLER Issue R2 Date 26 09 2011 CRN 7502 Page 63 B4 Configuration Flowchart ...
Page 74: ...GASGUARD IS CONTROLLER Issue R2 Date 26 09 2011 CRN 7502 Page 73 Appendix C Approvals ...
Page 75: ...GASGUARD IS CONTROLLER Issue R2 Date 26 09 2011 CRN 7502 Page 74 ...
Page 76: ...GASGUARD IS CONTROLLER Issue R2 Date 26 09 2011 CRN 7502 Page 75 ...
Page 77: ...GASGUARD IS CONTROLLER Issue R2 Date 26 09 2011 CRN 7502 Page 76 ...
Page 78: ...GASGUARD IS CONTROLLER Issue R2 Date 26 09 2011 CRN 7502 Page 77 ...
Page 79: ...GASGUARD IS CONTROLLER Issue R2 Date 26 09 2011 CRN 7502 Page 78 ...