4 . Setting the Laser Light Output Schedule
87
ML-3030AS/3015AS
Chapter 2 V
arious Settings
Introduction Part
Inst
allat
ion and
Preparation Part
Operating Part
Maintenance Part
Appendixes
SCHEDULE Screen (Flexible Waveform (CW))
How to see the displayed items
: Settable item
PEAK POWER
Sets the peak value of laser output (value when "POWER" are 100%). Regard-
ing the actual laser output value ("POWER"), set the ratio (%) to the peak value
supposing that the set peak value is the reference value (100%).
<Note>
The settable peak value of laser output differs depending on the model.
ML-3030AS: 50 to 270 W / ML-3015AS: 25 to 135 W
Scrolls the POINT display column of POINT 01 to POINT 20 to the right and left.
When a POINT is not displayed, press this button to display it.
RESOL
When this button is pressed, the selected setting resolution can be set from 1 s,
0.1 s, 0.01 s, or 0.001 s.
When the setting resolution is changed, the currently-selected schedule is
cleared and the initial value is set.
POINT 01
·
·
·
POINT 20
TSet the laser output time and laser output value (POWER [%]) at each point of
"POINT 01" to "POINT 20."
<Note>
There are limitations of settable values in combination with values of PEAK
POWER and REPEAT. For details, refer to "Limitations of Schedule Setting" on
page 100.
MODU
When this button is pressed, the modulation setting screen for the selected
schedule number opens. Blinks when the modulation function is enabled. The
function can be set on the MODULATION screen.
Fn
When this button is pressed, a window to select function is displayed and the fol-
lowing editorial assistant functions can be used.
RESET: Initializes the currently-selected schedule.
COPY:
Copies the currently-selected schedule to a temporary memory buffer.
PASTE:
Restores data from a temporary memory buffer to the currently-select
-
ed schedule.
⇒
For the common items in the upper/lower part of the screen, refer to page 59.
Summary of Contents for ML-3015AS
Page 21: ...Introduction Part...
Page 22: ......
Page 30: ......
Page 36: ......
Page 37: ...Installation and Preparation Part...
Page 38: ......
Page 52: ......
Page 53: ...Operating Part...
Page 54: ......
Page 163: ...Maintenance Part...
Page 164: ......
Page 175: ...Appendixes...
Page 176: ......