3
MECHANICAL IMPLEMENTATION
3.1
RPV311
3.1.1
MAIN FEATURES
Fan-less and no rotating part design
Trigger waveform recorder at 256, 128, or 64 points-per-cycle;
Continuous waveform recorder at 16 points-per-cycle;
Continuous disturbance recorder and trigger recorder (optional);
Trigger using Boolean logic equations;
Traveling wave recorder for fault location (optional);
MODBUS and DNP3 interface for SCADA integration (optional);
Synchrophasor measurement according to IEEE C37.118 (optional);
Power quality records:
o
Historical average at aggregation intervals of 1 or 10 minutes (optional);
o
Measurement and recording of harmonics up to the 50th order according to IEC 61000-4-7
(optional);
o
Measurement and recording of flicker according to IEC 61000-4-15 (optional);
Cross-trigger using standard network connection;
One-end fault location based on Takagi algorithm;
Flexible communication:
o
Two 10/100BaseT electrical Ethernet interfaces;
o
Two embedded optical Ethernet converters;
o
RS232 serial port for modem connection;
Support for IEC 61850:
o
Up to 320 binary inputs related to GOOSE messages (optional);
o
Two Ethernet ports for redundant connection (optional);
o
One Ethernet port for Process Bus (Sampled Values) connection (optional).
Local interface on the front panel;
4 dry-contact relays for remote signalling;
Fax and
/
or e-mail message after detection of a trigger. The fax can be sent to two different
destinations and the e-mail to four different destinations (optional).
Summary of Contents for Reason RPV311
Page 2: ......
Page 15: ...INTRODUCTION CHAPTER 1...
Page 34: ...SAFETY INFORMATION CHAPTER 2...
Page 45: ...HARDWARE DESIGN CHAPTER 3...
Page 56: ......
Page 57: ...CONFIGURATION CHAPTER 4...
Page 75: ...RPV311 Chapter 4 Configuration RPV311 TM EN 6 75 Figure 21 Email Fax configuration...
Page 77: ...RPV311 Chapter 4 Configuration RPV311 TM EN 6 77 Figure 22 Adding and editing voltage circuits...
Page 117: ...OPERATION CHAPTER 5...
Page 121: ...RPV311 Chapter 5 Operation RPV311 TM EN 6 121 Figure 46 Status monitoring sequence...
Page 123: ...RPV311 Chapter 5 Operation RPV311 TM EN 6 123 Figure 47 Monitoring sequence...
Page 128: ...Chapter 5 Operation RPV311 128 RPV311 TM EN 6 Figure 50 Equipment settings monitoring sequence...
Page 155: ...RECORDS CHAPTER 6...
Page 172: ......
Page 173: ...TW FAULT LOCATOR CHAPTER 7...
Page 183: ...PMU CHAPTER 8...
Page 189: ...MODBUS CHAPTER 9...
Page 193: ...DNP3 CHAPTER 10...
Page 196: ......
Page 197: ...GOOSE MESSAGE DETECTION CHAPTER 11...
Page 200: ......
Page 201: ...SOFTWARE RPV TOOLS CHAPTER 12...
Page 228: ......
Page 229: ...SOFTWARE RPV MANAGER CHAPTER 13...
Page 249: ...COMMUNICATIONS CHAPTER 14...
Page 261: ...INSTALLATION CHAPTER 15...
Page 295: ...Chapter 15 Installation RPV311 RPV311 TM EN 6 295 Figure 138 RA331 RA332 and RA333 dimensions...
Page 299: ...MAINTENANCE AND TROUBLESHOOTING CHAPTER 16...
Page 310: ...TECHNICAL SPECIFICATIONS CHAPTER 17...
Page 331: ...RPV311 Chapter 17 Wiring Diagrams WIRING DIAGRAMS CHAPTER 18...
Page 340: ...APPENDIX A...