![Airspan AirSynergy 2000 Installation Manual Download Page 24](http://html.mh-extra.com/html/airspan/airsynergy-2000/airsynergy-2000_installation-manual_2879128024.webp)
AirSynergy 2000 Installation Guide
Page 24
Commercial in Confidence
UGD-D01001 Rev B
4 Verify Prerequisites
Prior to installing the AirSynergy, verify the required safety, power, tools, parts and components.
Reference:
Set up requirements for the installation is detailed in the
Job Sheet
,
4.1 Verify Site Requirements
To set up the AirSynergy, an IP connection to a Netspan server is required.
4.2 Verify Installation Requirements
4.2.1 Verify the Tools
Note:
AirSynergy variants with Sunshield, front mounted and Switched Beam
antennas come pre-assembled from the production line.
Table 7 - AirSynergy installation tools
Tool
Use
Large flat bladed screwdriver
securing the pole straps
13mm wrench x 2
heavy-duty pole clamp option only
10mm or 13/32 inch wrench
AirSynergy securing flange nuts
Large pliers
Tightening cable glands - To fit 15mm
Knife
For stripping insulation
Wire cutters
Wire strippers
Cutting of insulation
Ring terminal crimp tool
Tilt-meter
If accurate down-tilt of antenna needs to be set
4.2.2 Verify the Parts and Kits
Table 8 - AirSynergy installation parts and kits
Installation Kit / Part Part No.
Consisting of
Note:
Main AirSynergy
parts
SYN-U-PMK-2
1 x AirSynergy Universal
Mounting Plate and pole
strap kit
Includes 2 pole straps
for poles up to 200mm
diameter (minimum
pole diameter 50mm)
SYN35-xx-xx-xxx-
xxx
AirSynergy unit(s)
Frequency band and
assembly type-specific
Verify order and
requirements to
ensure the correct
unit type is being
installed.
Optional Accessories