42
Hardware Installation
Installation
Switching from EI to CI Operating Mode
Special procedure for CI MSD
Refer to the
5973 inert MSD Hardware Manual
.
1
Vent the MSD.
2
Open the analyzer.
3
Remove the EI ion source.
4
Install the CI ion source.
5
Install the interface tip seal.
6
Pump down the MSD.
7
Set methane flow to 40%.
8
Bake out and purge the MSD for at least two hours.
9
If the vacuum gauge controller is on, turn it off.
10
Set up the software for CI operation. Verify that PCICH4.U is
loaded.
11
Select
Purge Cal Valve
from the Vacuum menu in the
Diagnostics/Vacuum Control view.
12
Set up the methane reagent gas flow.
13
Verify that there is no visible peak at m/z 32, and that the
peak at m/z 19 is less than 50% of that at m/z 17.
C A U T I O N
Electrostatic discharges to analyzer components are conducted to the
side board where they can damage sensitive components. Wear a
grounded anti-static wrist strap (see the
5973 inert MSD Hardware
Manual
) and take other anti-static precautions before you open the
analyzer.
C A U T I O N
Do not proceed without purging the calibration valve, or the analyzer
will be damaged.
Summary of Contents for 5973N
Page 1: ...Agilent Technologies 5973N and 5973 inert Mass Selective Detector Hardware Installation ...
Page 6: ...6 Hardware Installation ...
Page 20: ...20 Hardware Installation General Information ...
Page 59: ......
Page 60: ...G2589 90073 Agilent Technologies Agilent Technologies Inc Printed in USA August 2003 ...