Detector Startup

Complete Startup (from total shut down)

1

Turn on the detector and establish carrier gas flow.

2

Turn on the vacuum pump with the toggle button located on the front panel 
of the Detector.

3

Turn the instrument from Standby to On, and allow the system to evacuate 
for approximately 1 minute.

4

Turn on the air to the ozone generator and set the regulator inside the front 
door of the Detector to between 3 and 6 psig.

5

Turn on the ozone generator.

6

Turn on the Interface Controller with the toggle on the back panel of the 
box.

Daily Startup (from daily shutdown)

1

Turn the instrument from Standby to On, and allow the system to evacuate 
for approximately 1 minute.

2

Turn on the air to the ozone generator and set the regulator inside the front 
door of the Detector to between 3 and 6 psig.

3

Turn on the ozone generator.

Detector Shutdown

Daily Shutdown (Standby Mode)

1

Turn off the ozone generator with the button on the front of the Detector.

2

Turn down the oxidant flow to 0 with the regulator located in the front door 
of the Detector.

3

Turn the Detector power to Standby.

It is recommended to leave the vacuum pump and Dual Plasma Controller 