3. LIFTING
General comments:
▪
Wear personal protective equipment (PPE) properly.
▪
Personnel must have received the required training.
▪
Ensure the safety of personnel at all times. Keep all unnecessary personnel out of the handling area.
▪
Direct contact with hard materials must be avoided.
▪
Labels and/or tape on the edge of the pack must be removed before handling.
▪
Lifting gear must be properly centred.
▪
Each sheet must first be lifted slightly and then moved away from the others.
▪
Care must be taken to prevent scratches, especially when handling silvered glass, by ensuring that
the edge of one sheet does not rub against the surface of another.
▪
Suction lifting gear and other hoisting equipment must comply with prevailing regulations and be
approved by the relevant authorities.
▪
Personnel must check that the suction pads are adhering correctly before handling.
Prior to the process of mirror, it is advisable to follow below specific handling according to each
method:
Specific handling:
Manual Handling:
▪
Adjust
manpower quantity based on size of glass for safety reason.
▪
Only lift the glass wearing safety gloves and safety shoes.
▪
It is advisable to avoid any contaminant around the cut-size of mirror.
Stock Sheets:
▪
Sheets must be lifted using either suction lifting gear or an automatic unstacking machine.
▪
Proceed as described in the general comments.
A-Racks:
▪
Set the A-racks on a stile inclined at a slight angle (4° - 8°).
▪
Cut the strapping.
▪
Remove or cut the front plastic cover and then the two side covers.
▪
Proceed as described in the general comments.
Endcaps:
▪
Set the endcap on a stile inclined at a slight angle (3° - 4°).
▪
Cut the vertical strapping.
▪
Remove the upper cover and then the two side covers.
▪
Remove the plastic protecting the glass.
▪
Proceed as described in the general comments.
Safety back products:
▪
Static electricity may build up while unloading safety back products after transport.
▪