![Aerotech Automation1 XR3 Series Hardware Manual Download Page 29](http://html1.mh-extra.com/html/aerotech/automation1-xr3-series/automation1-xr3-series_hardware-manual_2863033029.webp)
Chapter 2: Installation and Configuration
Unpacking the Chassis
IMPORTANT
: All electronic equipment and instrumentation is wrapped in antistatic
material and packaged with desiccant. Ensure that the antistatic material is not damaged
during unpacking.
Inspect the container of the XR3 for any evidence of shipping damage. If any damage exists, notify the
shipping carrier immediately.
Remove the packing list from the XR3 container. Make sure that all the items specified on the packing list
are contained within the package.
The documentation for the XR3 is on the included installation device. The documents include manuals,
interconnection drawings, and other documentation pertaining to the system. Save this information for
future reference. Additional information about the system is provided on the Serial and Power labels
that are placed on the XR3 chassis.
The system serial number label contains important information such as the:
l
Customer order number (please provide this number when requesting product support)
l
Drawing number
l
System part number
The XR3 power label contains the factory configured AC power requirements.
DANGER
: Update the AC power label if you reconfigure the AC Input Voltage.
WARNING
:
Heavy Object
1. Lift this product only by the base.Do not use the cables or the connectors to lift or
move this product.
2. Do not use the handles on the front of the product to lift or move this product. Use
the handles only to slide the product in and out of its enclosure.
XR3 Hardware Manual
Chapter 2: Installation and Configuration
www.aerotech.com
29