Installation and Commissioning
The purpose of this section is to enable the user to correctly assemble, commission, and install their AQM.
Undertaking the commissioning procedure correctly is an important part of the product
transfer process and customer acceptance. It confirms that you have received the product in
good working order and it has been shipped to you without damage.
The full commissioning process will require gas calibration and flow equipment (not supplied with the AQM).
In the absence of gas calibration and flow measurement capabilities, measurement of outside air over a 24
hour period and comparison of this data with measurements from a local “reference” air monitoring station
will provide evidence of correct span operation.
2.1. Unpacking
a) Examine the Shockwatch label on the side of the shipping box. If the indicator is
red
do not refuse
shipment. Make a notification on delivery receipt and inspect for damage. If damage is discovered,
leave item in original packaging and request immediate inspection from carrier within 15 days of
delivery date (3 days international).
b) Verify the serial number label on the documentation matches the serial label on the AQM (located on
inside of enclosure).
c) Verify that all components have been shipped as per the packing slip. Contact your Distributor or
Aeroqual if you suspect any parts are missing.
d) Unpack the AQM.
e) Remove all internal shipping/packaging material from the AQM enclosure.
f) Retain the packaging.
Note: Always transport the AQM in the cardboard box and two piece aluminum skins with foam
packing provided to avoid breakages. Wrap all peripheral assemblies in their original packaging also.
The AQM is a sensitive instrument and should be transported with care.
2.2. Assembly
2.2.1. Connect Mains Power
Caution: The high voltage mains supply must be wired by a certified electrician in
compliance with local electrical regulations
.
Locate the 3 port junction box on the outside of the AQM cabinet:
Unscrew from the enclosure
Remove the three gland nuts
Insert a small flat bladed screwdriver to lever the retaining clips, on each side where indicated
Wire a mains electrical cable to the terminal block provided (Live, Ground and Neutral).
Close the lid to the 3 port junction box and replace the three gland nuts.