5
5.3 Ceiling installation
The unit must be installed in the following position.
It is important that the unit is completely flat in order for the condensation drainage to work properly.
5.a
Prepare the surface where the unit is to be mounted. Make sure that the surface is flat, leveled and that it supports the weight of the unit. Perform the
installation in accordance with local rules and regulations.
Close the two condensation holes on the casing side opposite the access panel using 2 plugs each hole, one internally and the other externally and seal
them to provide water and air tightness.
5.b
Use appropriate plugs and rods or screws (not supplied) to fix the unit to the ceiling. It is recommended to fit the unit with anti-vibration mounts (not
supplied).
5.c
Assure that the unit is completely flat once mounted to the ceiling, for the condensation drainage to function properly.
5.d
Connect the condensation elbow(s) to the drainage hole(s) on the access panel: in case close and seal the non-used hole with the supplied plugs (2 plugs
each hole). Make sure of water and air tightness of all connections. The condensation pipe connection must be done in a way that makes easy to remove
the access panel for the service operation. It is recommended to use a U-bend in the condensation drainage pipe.
5.e
Connect the unit to the duct system. Make sure that all necessary accessories are used to create a functional ventilation solution.
Connect the unit
electrically according to point 5.5. Check that it starts up correctly.
Fig 5.a
Fig. 5.b
Fig. 5.c
Fig. 5.d
Fig. 5.e
SPIRIT LEVEL
SPIRIT LEVEL
H=min. 60mm
holes to be closed
Summary of Contents for QR200A