background image

THREE-PHASE
GRID-TIED OLAR INVERTER
QUICK INSTALLATION GUIDE

AS-IC01-2 SERIES

THANK YOU FOR CHOOSING AEG

Follow these instructions to successfully install your 
AEG solar inverter of the series AS-IC01-2:

AS-IC01-2 three-phase grid-tied solar inverter, 2 MPPT:
AS-IC01-4000-2/5000-2/6000-2/8000-2/10000-2

    

  CONTENTS 

1. Safety Recommendations
2. Product unpacking and inspection
3. Before installation
4. Mechanical installation
5.. Electrical installation
6. Operation
7. More information / Contacts

   1. SAFETY RECOMMENDATIONS 

General safety recommendations

• 

Only qualified electricians are allowed to install the 

inverter.

•  Make sure the installation site is not accessible to 

children or non-authorized personnel.

•  Remove metal accessories such as rings or bracelets 

before installation and electrical connection to avoid 
electric shock.

Product safety recommendations

•  Do not put and install the inverter on or close to 

combustible materials. 

•  Install the inverter far from devices with strong 

electromagnetic interference. 

•  To avoid product damage, ensure the inverter input 

voltage does not exceed the maximum input voltage.

•  Ensure a stable installation and a reliable electrical 

connection, as well as proper grounding of the inverter; 
improper connection or no grounding may cause the 
inverter to stop functioning.

•  To avoid irreparable damage, ensure that the positive 

and negative poles of solar modules are not grounded. 

!

   2. PRODUCT UNPACKING AND INSPECTION

2.1 Product inspection

Double-check the order information and the product na-
meplate to ensure the products are of the ordered type 

and that the package is not damaged. Should you find 

any problems, contact your supplier as soon as possible.

In the packaging of your AEG inverter you will find:

Model 
AS-IC01-xxx-2

4000-2
5000-2
6000-2
8000-2
10000-2

Inverter

1

Installation bracket

1

Quick installation guide

1

Communication connector

1

Expansion bolts

4 (M6*60)

DC connector

1

AC connector

1

Table 1: Three-phase inverter packing list

2.2 Product look

Front and side view of AEG AS-IC01-2 three-phase grid-
tied solar inverter

    

3. BEFORE INSTALLATION

Before installing your AEG grid-tied solar inverter, please 
take in consideration the following aspects:

3.1 Installation place

Select the installation place considering that:
1- The environment temperature should be between 
-25°C and 60 °C.
2- The insatllation surface should be perpendicular to the 

horizontal line. Please refer to figure 2 here below.

Figure 1: Installation space (mm)

Figure 2: Installation position

3.2 Cable specifications

Select connection cables according to the below table: 

Model 

DC side

AC side

Cross-section Mini cross-section

AS-
IC01-4000-2/
5000-2/
6000-2/
8000-2/
10000-2

4 mm

 

(12 AWG)

4 mm

(12 AWG)

 

Table 2: Cable specifications

1

2

3

4

   
    4. MECHANICAL INSTALLATION

We take as reference a typical installation environment, 
such as a concrete wall.

Figure 3: Installation brackets, AS-IC01-2 4000 to 10000

Model 

Installation hole

A x B

AS-
IR01-4000-2/
5000-2/
6000-2/
8000-2/
10000-2

260 mm x 45 mm

 

Table 3: Size of installation bracket

Follow these steps to install your AEG inverter:

1- Define the installation hole with aid of the installation 
bracket, and use the expansion bolts to fix the installation 

brackets to the designed location on the wall.

2-Lift the inverter to suspend it to the installation 
brackets and fasten with M8 hex socket cap screws.

3- Fasten the M5 screws and fasten the inverter to the 

bracket. Make sure the inverter is fastened firmly to the 

bracket.

Figure 4: Installation brackets, AS-IC01-2 4000 to 10000

   5 . ELECTRICAL INSTALLATION

Follow the next step to carry out the electrical wiring of 
your AEG inverter:

1- Before connecting the three-phase AC grid cable to 
the inverter, take lightning and short circuit protection 
measures in accordance with the local electrical safety 
codes.

2- As shown in Figure 6 below, connect and fasten L1, L2, 
L3, N (optional) and PE conductors of the three-phase 
common grid to the AC terminal, and then connect the 
terminal to the inverter´s AC port.

3- Fix and connect the DC output cables of the PV 
module with the matching DC connectors, and then 
connect the connectors to the inverter´s DC port.

Figure 5: Electrical wiring of the inverter

Figure 6: Connection of the AC to the inverter

DOCUMENT REVISION: PL201803 EN V.1-18

   
    6. OPERATION

6.1 Pre-operation inspection

Before starting inverter operations, please make sure to:

1- Check that the voltage of the components is in the 
allowed input voltage range of the inverter.
2- Check that the voltage of the AC grid is regular.
3- Check that the inverter is well grounded.
4- Ensure that all the switches are positioned on „OFF“
5- Ensure that all electrical safety precautions are clearly 

identifiable at the installation site.

6- Make sure that the WiFi stick (if used) is well 
connected.

6.2 Commissioning

To start the inverter:
1- Switch on the integrated DC switch.
2- Should you wish to change the default country, 
currency and time settings (Netherlands, EUR, GMT+1) 
of the inverter, you can use the External Display or the 
WiFi Stick (local monitoring mode via the app AEG 
InverterControl). 

In this case Install the WiFi Stick and the App as 
described in chapter 3 and 4.1 (page 6) of this guide, 
then connect your phone with the wireless network „AEG 
WiFi“ (generated by the WiFi Stick). Launch the App and 
select: Local Monitoring > click on your WiFi Stick picture 
> More > Parameter > change the individual parameters)

3- Switch on the breakers at the AC side
4- Check the LED indicators and the information 
displayed on the LCD screen / on the external display:

Run  Alarm  Fault

The green indicator blinks, the 

other  indicators  are  off:  the 

inverter is on and is in self-
inspection mode

Run  Alarm  Fault

The green indicator is on, the other 

indicators  are  off:  the  inverter  is 

in power generation mode after 
self-inspection. The inverter was 
successfully commissioned

Run  Alarm  Fault

Run  Alarm  Fault

„Alarm“ or „Fault“ indicators are on 
or blinking: the inverter is on, but 
faults are occurring

For the complete list of errors and warnings, see the 
extended version of the installation manual at 
www.aeg-industrialsolar.de/aeg-inverter-service

6.3 Accessories (Complements) and wiring

Complements to the inverter are :
-the External Display (optional)
-the WiF Sticki

   

Figure 8: Complements to the inverter

6.4 Regular maintenance

To carry out maintenance, inspection or troubleshooting 
operations on the inverter, stop the device as follows:

1- Switch off the breakers at the AC side.
2- Switch off the integrated (inverter´s) DC switch

3- Contact your local distributor or the AEG Inverter 
Service.

  

 7.  MORE INFORMATION / CONTACTS

You can download the extended version of the AEG grid-
tied three-phase solar inverter and the related Warranty 
Conditions at www.aeg-industrialsolar.de/aeg-inverter-
service. 

Solar Solutions GmbH
Schneckenhofstrasse 19
60596 Frankfurt am Main
Germany
[email protected]

Last updated: March 2018 