Total Access
®
3000/3010 System Manual
6TADLP740-1E
TOTAL ACCESS 3000/3010
DLP-740
Page 1 of 10
© 2003, ADTRAN, Inc.
Perform Steps Below in the Order Listed
1.1
Provisioning the DS-3 Multiplexer Module
NOTE
References to common, but differing, parameters between the Total Access
3000 and the Total Access 3010, such as number of slots, will be conveyed
by the convention a/b. “A” represents the Total Access 3000 parameter and
“b” represents the Total Access 3010 parameter. For example, the differing
number of access slots in the two platforms, 28 for the Total Access 3000 and
22 for the Total Access 3010, would be displayed “28/22.”
1.1.1
Introduction
This section provides step-by-step instructions for the provisioning of a Total Access
3000/3010 DS-3 MUX module. In the case of 1:1 protection, instructions are included
for the provisioning of the working and protect modules.
1.1.2
Prerequisite Procedures
The following procedures must be completed prior to provisioning the DS3 MUX
module and are assumed to have been completed. If necessary, refer to the appropriate
documentation before proceeding. The prerequisite procedures include:
•
Installation and wiring of Total Access 3000/3010 shelf and SCU – NTP-501
•
BNC module installation – DLP-708
•
Coaxial cable installation – PREP-401, DLP-709
•
Physical installation of DS-3 MUX Module – NTP-504
1.1.3
Tools Required
A pen or pencil will be required to operate the recessed APS button on the faceplate of
the unit.
1.1.4
Materials Required
•
Total Access 3000/3010 DS-3 MUX module (two modules for 1:1 protection
switching applications)
1.2
Preparing to Provision the Primary MUX (slot A)
NOTE
If MUX Auto-Provisioning is enabled in the SCU and a DS-3 MUX unit is
subsequently removed and replaced with another DS-3 MUX unit, the SCU
will automatically download the provisioning settings,
including
Service
State, to the replacement DS-3 MUX.