3-44 ADS
Manual
¾-Band Mount
Perform the following procedure to mount the Peak Combo Sensor
(when applicable) in a pipe using the ¾-band mount:
1.
Use a hacksaw to cut the band to the appropriate length. Cut
the band so that, once installed, it will run approximately ¾ of
the circumference of the pipe.
2.
Locate the sensor at a position on the band based on installing
the long end of the band (end extending almost completely up
one side of the pipe) on the left side of the incoming pipe
(upstream from the manhaole) and the existence of silt at the
bottom of the pipe. ADS recommends reserving the left side of
the pipe for the long end of the band to accommodate the
sensor cable and a silt mount adapter, when applicable.
If silt is not present
, locate the sensor on the band so it will
be at the bottom center of the pipe once installed.
If silt is present
, locate the sensor slightly up the long end
(left side) of the band so that it will be above the silt level
once installed. However, make sure it will not be more
than 45 degrees from the bottom center of the pipe (i.e.,
7:30 position).
Peak Combo Sensor mounted using a ¾-band mount in the pipe with and
without silt
Summary of Contents for Intrinsically-Safe TRITON+
Page 19: ...1 12 ADS TRITON Manual Control Drawing ...
Page 25: ...1 18 ADS TRITON Manual First page of the TRITON ATEX Certificate ...
Page 27: ...1 20 ADS TRITON Manual First page of the TRITON IECEx Certificate of Conformity ...
Page 29: ...1 22 ADS TRITON Manual CSA Certificate of Compliance Page 1 ...
Page 30: ...Introduction 1 23 CSA Certificate of Compliance Page 2 ...
Page 32: ...Introduction 1 25 Sample TRITON Declaration of Conformity Page 2 ...