AddEnergie SmartDC Installation Manual Download Page 1

SmartDC

TM

-V2

 

Installation Guide

Summary of Contents for SmartDC

Page 1: ...SmartDCTM V2 Installation Guide...

Page 2: ...Notice V05 2017 04 10 Table of contents Security 3 Specifications 4 Dimensions 5 Exterior preview of the station 6 Interior preview of the station 7 Typical installation 8 Site preparation 9 Installin...

Page 3: ...s and installed by a certified electrician 5 Communicate with a certified contractor certified electrician or trained installer to ensure compliance with local building code regulation security standa...

Page 4: ...tion bloc 350 MCM max for the phases 3 0 max for the neutral Nominal voltage supply Three phase 480Y 277V must be protected by a 100A three phase over current protection device Maximum power consumpti...

Page 5: ...L RIGHTS RESERVED Information and Specifications Contained in this Document are Subject to Change Amendments and Additions at any Time Without Notice V05 2017 04 10 Dimensions 200cm 79po 83cm 33po 119...

Page 6: ...ment are Subject to Change Amendments and Additions at any Time Without Notice V05 2017 04 10 Exterior Preview of the Station A B D E F C G J I H A Locking door handle B Start button C Stop button D D...

Page 7: ...ions Contained in this Document are Subject to Change Amendments and Additions at any Time Without Notice V05 2017 04 10 Interior Preview of the Station A Power cable access B Three phase and neutral...

Page 8: ...t any Time Without Notice V05 2017 04 10 Typical Installation A Electrical equipment cabinet metering protection and distribution B Power cable three phase 480Y 277 Volts 100A NEUTRAL GROUND C SmartDC...

Page 9: ...nd stabilized as required so that it is not affected by freezing 5 An electric conduit of appropriate diameter based on the electric wire gauge must bring the electric cable under the station s perime...

Page 10: ...ncrete Slab 1 It is recommended to use stainless steel inch 6 4 mm concrete wedge anchors not included 2 Drill holes in the concrete slab of diameter and depth appropriate for the anchors according to...

Page 11: ...onto the Base 1 Remove the access plate to allow the passage of the power cable 2 Place the station onto its base making sure to pass the power cable through the access hole 3 Punch a hole in the acc...

Page 12: ...ent are Subject to Change Amendments and Additions at any Time Without Notice V05 2017 04 10 1 Connect the three conductors into the three phase power terminal 2 Connect the NEUTRAL conductor into the...

Page 13: ...ree phase 480Y 277V voltage is within specifications Once the station is on 1 Close and lock the charging station s casing door Putting the station into service 1 After the station has been turned on...

Page 14: ...UST BE PERFORMED BY ADD NERGIE It consists of 1 Cleaning or replacing the cooling system filters It is important to maintain proper airflow inside the station to adequately cool the power modules 2 In...

Page 15: ...denergie ca Installation or commissioning questions 877 505 2674 ext 203 Add nergie Technologies Inc Eastern office 2327 Versant Nord Boulevard office 120 Qu bec QC G1N 4C2 CANADA Central office 7420...