Operation
81/ 100
Oleolift-C
■
Arrange for the quarterly maintenance of the pump station,
Chapter 5.1 "Quarterly maintenance of the pump station".
■
Arrange for half-yearly maintenance of the light liquid separator,
Chapter 5.2 "Bi-annual maintenance of the light liquid separator"
■
Arranging for the general inspection of the light liquid separator,
Chapter 5.3 "5-year general inspection of the light liquid separator"
4.8 Self-monitoring of the light liquid
separator
IMPORTANT
■
The functionality and condition of the separator plant must be controlled at least once
a month by the operator, owner and/or by an expert assessor using the following
measures (applies only to Germany). Provisions in other countries can vary).
■
If defects are identified during the tests or inspections, then the light liquid separator
plant must not be put back into service until these defects have been remedied.
Controls executed, possible defects and their remedial works must be documented in the
operating log.
Scope of the monitoring work:
Î
Check the condition of the separator chamber and the installation parts (if visible from above).
Î
Check the condition of the sampling point.
Î
Remove coarse floating matter from the water surface area.
Î
Visually check the permeability of the coalescent insert: If the water level in the
separator chamber is more than 100 mm below the upper edge of the partition wall,
proper function is ensured. Otherwise implement intermediate cleaning,
Chapter 4.8.2 “Cleaning the coalescence insert”.
Î
Check storage capacity:
■
80 % or 100 % of the maximum storage quantity of light liquid is automatically
determined and displayed.
■
The height of the sludge level is to be determined by auxiliary means provided
by the customer.