Installation and commissioning guide
1ZSC000562-AAK EN, REV. 2, 2019-07-03
71
4.
Remove the hose, and install the cover (1).
G004471
Torque
10 Nm
End of instruction
9.3 Transportation without transformer oil in the transformer
Overview
The tap-changer must be drained from transformer oil, if the transformer is drained.
Procedure
1.
Drain the transformer oil from the tap-changer.
CAUTION!
Do not transport the tap-changer filled with transformer oil if the transformer oil has been
drained from the transformer. This will help to prevent damage to the tap-changer.
End of instruction
Summary of Contents for VUBB
Page 14: ...14 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 28: ...28 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 52: ...52 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 60: ...60 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 68: ...68 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 72: ...72 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 74: ...74 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 76: ...76 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...