Procedure
1. Loosen the screws (A).
2. Insert the cable connector into the
terminal block (B).
3. Connect these wires:
1. Earthing wire (C)
2. Neutral wire (D)
3. L1 (E)
4. L2 (F)
5. L3 (G)
Refer to section
4. Tighten the screws (A) to the correct
torque. For the specification, refer to
section
.
7.3.3
Connect the AC input cable (UL portfolio)
Preliminary requirements
•
Torque screwdriver
•
AC input cable (1 phase)
Procedure
1. Loosen the screws (A).
2. Strip the wires. For the specification,
refer to section
.
3. Insert the cable connector into the
terminal block (B).
4. Connect the below wires:
1. Earthing (grounding) wire (C)
2. Neutral wire (D)
3. L2 AC input wire (F)
4. L1 AC input wire (E)
Refer to section
5. Tighten the screws (A) to the correct
torque. For the specification, refer to
section
.
7.3.4
Secure the cables
Preliminary requirements
•
Torque screwdriver
•
Strain relief for the cable
B
E
D
F
G
C
A
B
E
D
F
C
A
Electrical installation
BCM.V3Y01.0-EN | 002
41