8.1 Prepare for commissioning
Danger: Hazardous voltage
Do not commission the EVSE. Only a service engineer of the manufacturer is qualified to
commission the EVSE
The below requirements and operations are Owner/Qualified installer responsibilities:
1. The Qualified installer should tells to the owner that the EVSE is ready for commissioning.
2. The Owner/Qualified installer should check that the site is in accordance with these requirements:
• The EVSE is installed
• AC input power is available from the grid provider
• Be present during the commissioning, for assistance and to energize the power to the EVSE on the power
distribution board
• Internet access is available, through cellular (default) or wired Ethernet connection.
In case of cellular connection, the signal strength must be greater than -85 dBm and should be measured
with a cellular network signal meter. Handheld mobile phones are not recommended for assessing signal
strength since they are not reliable measuring devices. Refer to
• An EV must be available with a compatible connection. If the EVSE has more than one connection type, an
EV of each type must be available
• Night illumination must be sufficient to easily see the charging cables and other obstacles around the
EVSE
• The site operator or owner is available to receive instructions from the service engineer of the manufacturer
3. The Owner/Qualified installer should check that these data are available:
• Contact data of the contact person on site
• Address of the EVSE
• Site name
• Exact location of the EVSE: longitude and latitude. If there are more EVSEs on one location, make sure that
the coordinates are slightly different (at least 0.0001 degree) so that the EVSEs are not at the same
location on the map.
• Specification of the external AC protection devices at the power distribution board
• Installation date
• Special remarks, for example to decline the authorization for the service engineer of the manufacturer to
take photos
• Photo of the surroundings/cables arrival of the EVSE
8.2 Prepare before use
• Appoint a site operator and an installation engineer, if these are other persons than you.
• Make sure that the EVSE is installed according to the instructions in this manual.
• Make an emergency plan that instructs people what to do in case of an emergency.
• Give instructions to each end user:
−
Emergency stop. Refer to section
“8.3.3. Emergency stop of a charge session”
.
−
Charge session. Refer to section
.
• Make sure that the manufacturer service or authorized service partner commissions the EVSE. If not, contact
the manufacturer when the EVSE is ready for commissioning.
General risk:
Make sure that you have approval of the manufacturer to use the EVSE after commissioning. After
approval, do not perform any change on the EVSE.
• Make sure that the space around the EVSE cannot get blocked.
• If necessary, remove condensation before use, to prevent damage to the EVSE.
• Start/stop a charge session. Refer to section