Procedure
1. Loosen the screw of the connection on
the terminal.
2. Install the ferrule in the connection of
the terminal.
3. Tighten the screw to the correct
torque. For the specifications, refer to
section
4. Make sure that unused wires are
protected and cannot touch metal
parts.
5.8
Cable management system installation (option)
5.8.1
Prepare the cable management system
Preliminary requirements
•
The package material is removed.
For the torque specifications, refer to section
.
Procedure
1. Clean these parts:
•
Floor around the EVSE to lay the
cables
•
Eye-bolt holes on the top of the
EVSE
•
EV charge cables
2. Put the cable management system
horizontally.
3. Remove the travel bolt (A).
4. Do a check on the number of
counterweights that are required for
the EV charge cable. Refer to section
.
•
If the number of required counterweights is 5, go to step 5.
•
If the number of required counterweights is more or less than 5, mount the
.
5. Remove the fasteners (B) on the back of the head.
6. Remove the modular counterweight (C).
7. If it is necessary, do these steps:
a. Remove counterweights (D) to be compatible with the type, rating and
length of the EV charge cable.
b. Cut the wire of the cable management system to the correct length.
8. Insert the modular counterweight in the duct.
B
A
1
3
2
A
D
B
C
Installation
9AKK108466A3703-EN | 001
55