11.5.11.2
Completing the test
SEMOD175058-66 v4
Continue to test another function or end the test by changing the
TESTMODE
setting to
Off
. Restore connections and settings to their original values, if they were
changed for testing purposes.
11.5.12
Broken conductor check BRCPTOC
SEMOD175021-3 v5
Prepare the IED for verification of settings outlined in Section
11.5.12.1
Measuring the operate and time limit of set values
SEMOD175021-7 v6
1.
Check that the input logical signal BLOCK to the BRCPTOC function block
is logical zero and note on the local HMI that the output signal TRIP from the
BRCPTOC function block is equal to the logical 0.
2.
Set the measured current (fault current) in one phase to about 110% of the set
operating current
IP>
.
Observe to not exceed the maximum permitted overloading of the current
circuits in the terminal.
3.
Switch on the fault current and measure the operating time of BRCPTOC.
TRIP is controlled by Gate 13 in the configuration.
Use the TRIP signal from the configured binary output to stop the timer.
4.
Compare the measured time with the set value
tOper
.
5.
Activate the BLOCK binary input.
6.
Switch on the fault current (110% of the setting) and wait longer than the set
value
tOper
.
No TRIP signal should appear.
7.
Switch off the fault current.
8.
Set the measured current (fault current) in same phase to about 90% of the set
operating current
IP>
. Switch off the current.
9.
Switch on the fault current and wait longer than the set value
tOper
.
No TRIP signal should appear.
10. Switch off the fault current.
11.5.12.2
Completing the test
SEMOD175021-42 v4
Continue to test another function or end the test by changing the
TESTMODE
setting to
Off
. Restore connections and settings to their original values, if they were
changed for testing purposes.
11.5.13
Voltage-restrained time overcurrent protection VRPVOC
GUID-764DA61A-D987-4358-867A-DA43ADDC6E57 v5
Prepare the IED for verification of settings outlined in Section
Section 11
1MRK 505 378-UEN A
Testing functionality by secondary injection
192
Line differential protection RED670 2.2 IEC
Commissioning manual
Summary of Contents for RED670 Relion 670 series
Page 1: ...RELION 670 SERIES Line differential protection RED670 Version 2 2 IEC Commissioning manual ...
Page 2: ......
Page 18: ...12 ...
Page 36: ...30 ...
Page 68: ...62 ...
Page 72: ...66 ...
Page 108: ...102 ...
Page 278: ...272 ...
Page 282: ...276 ...
Page 288: ...282 ...
Page 306: ...300 ...
Page 307: ...301 ...