76 Start-up
First start up
First start-up procedures
Set the AC line circuit breaker to ON at the AC distribution board.
Wait for the inverter to start.
After the start-up sequence, select the user
interface language with the up and down arrow
keys.
English is the default language.
After you select the language, wait for the control
unit to load the language.
The
First start
assistant opens when the inverter
starts for the first time and until the settings are
confirmed.
Push the right softkey to continue.
Next, set the date, time and their formats.
To set the date, select
Date
and push the right
arrow key.
Set the date with the up and down arrow keys.
Move between the day, month and year with the
right and left arrow keys.
Push the right softkey to save the date.
Summary of Contents for PRO-33.0-TL Series
Page 1: ...ABB solar inverters Product manual PRO 33 0 TL string inverters ...
Page 4: ......
Page 10: ...10 Table of contents ...
Page 32: ...32 Hardware description ...
Page 40: ...40 Installation requirements ...
Page 70: ...70 Electrical installation ...
Page 74: ...74 Installation checklist ...
Page 110: ...110 Maintenance ...
Page 134: ...134 Navigation map The navigation map ...
Page 136: ...Contact us www abb com solarinverters 3AUA0000123261 Rev B EN 2015 06 18 ...