Operation Manual / Power2 850-M / 4.1 Low-pressure stage
4 Disassembly and assembly / 4.8 Removing the cartridge group
© Copyright 2019 ABB. All rights reserved.
HZTL4062_EN
Revision A
March 2019
Fig. 13: Moving out cartridge group 2
7. Carefully move out cartridge group.
8. Put cartridge group into the fixtures in the turned-over toolbox cover.
9. Remove plate (90032), screw (90656), nut (90432) and plates (90031).
10. Remove the press-off screws (90920).
11. Remove O-rings (42017 / 42018).
CAUTION
Damage to cartridge group and toolbox cover
The turned-over toolbox cover may only be used as intermediate storage for
the cartridge group.
u
The cover must be on a level surface.
u
The cover may not be used to transport the cartridge group.
Fig. 14: Putting down cartridge group onto cover