ABB MOD 30ML Demonstration Manual Download Page 1

ABB Instrumentation

MOD 30ML Demonstration Guide

INDUSTRY:  Chemical / Pharmaceutical

REACTOR.DOC  11/8/99

Batch Reactor Demonstration

Unit Reactor Control

Introduction

Control of a batch reactor includes sequential and continuous elements, and tight control of the reaction
temperature. Ideally, only one device is used to perform both types of control, with a common local display
interface providing complete process information.  The following demonstration will show:

 

integration of automatic sequential and continuous control

 

front panel display of sequence steps

 

cascade control

 

front panel recipe selection and entry of recipe data

 

manual control of sequence steps through front panel

The Control System

The batch reaction is conducted according to a definite time-temperature cycle.  Figure 1 illustrates a typical
cycle of many industrial processes.

Reactants are added to the reactor at room temperature; the reaction mass is heated to reaction temperature;
the reaction is carried out to form products; the batch is cooled; and the reactor is emptied.  Total batch time
in reactors used in the manufacture of PVC or polystyrene, for example, is approximately fourteen to
eighteen hours.  The progression of the batch cycle is controlled by the sequence operation.   It may
sometimes be necessary for the operators to pause, stop, or manually advance the cycle to another step.

Summary of Contents for MOD 30ML

Page 1: ...t panel recipe selection and entry of recipe data manual control of sequence steps through front panel The Control System The batch reaction is conducted according to a definite time temperature cycle Figure 1 illustrates a typical cycle of many industrial processes Reactants are added to the reactor at room temperature the reaction mass is heated to reaction temperature the reaction is carried ou...

Page 2: ...rol and temperature cascade control Once started the batch cycle will progress automatically unless it is switched to manual mode Operator Changes The following operations may be done from the front panel displays Batch initialization Recipe selection Recipe parameter entry Manual advance of sequence Initial Conditions Batch AUTO OFF Note once the batch has been started Line 2 will indicate the Ti...

Page 3: ...ype controller action gain reset Benefit Commissioning activity can take place through front panel of instrument 3 Activity Display recipe selection by returning to main batch display and holding down scroll key Enter tuning password of 1 if required the tuning password from the previous activity may still be in effect Select recipe 1 using up down arrows and ENT Look for Once tuning password is e...

Page 4: ...eturn to main Batch display Press AUTO key to start the batch Look for Batch status changes to RUN Setpoint status changes to REMOTE Step indication on Line 6 changes to START then FILL Activity Scroll to fill display Look for Fill A and Fill B flow rates displayed on lines 1 and 2 left and middle bar Reactor level displayed on Line 6 and right bar Benefits Initiation of batch from front panel aut...

Page 5: ...N Press MAN key again to return batch cycle to automatic control Look for Batch status on line 2 changes to AUTO Batch resumes automatic control in COOL step Activity Scroll to TIC 100 display Look for Temperature setpoint ramping down to cool setpoint Benefits Manual control of batch cycle from front panel without need of external operator terminal Integration of sequential and continuous control...