Illustration/Note
Action
Connect fixing side cabling and hoses with floor
cables.
9
Test run
Illustration/Note
Action
Switch on the power.
1
Run a few strokes in jogging mode and check
that the chain is gliding properly upon itself and
is correctly adjusted sideways.
2
Run the system at low speed and insure that
everything runs freely and smoothly without the
chain, cables and/or hoses binding.
3
Adjust the chain position or alignment, if
needed.
4
Adjust the position and length of cables and/or
hoses, if needed.
5
If adjustments are made, repeat steps
to
6
Tighten all screws.
7
The track is now ready to be powered up to full
speed and duty cycle.
8
Check the tightening torque on fastening screws
after 500 cycles. Adjust, if needed.
The use of serrated lock washers, snap rings
and other locking means is not permitted in this
part of the track.
Moving back the carriage
Illustration/Note
Action
Move back the carriage and secure it to the
drive train bracket with the screws.
1
Refit the brake release unit and strap the brake
release cables to the carriage.
2
See
.
Refit the covers.
3
Mark the cables with a paint pen on both sides
of the strapping.
4
DANGER
Make sure all safety requirements are met
when performing the first test run. These are
further detailed in the section
cause injury or damage on page 24
.
5
See
Perform a test run before powering up the track
to full speed and duty cycle.
6
Continues on next page
248
Product manual - IRBT 2005
3HAC051130-001 Revision: F
© Copyright 2015 - 2018 ABB. All rights reserved.
4 Repair
4.9.1 Replacing the cable chain
Continued
Summary of Contents for IRBT 2005
Page 1: ...ROBOTICS Product manual IRBT 2005 ...
Page 8: ...This page is intentionally left blank ...
Page 44: ...This page is intentionally left blank ...
Page 148: ...This page is intentionally left blank ...
Page 284: ...This page is intentionally left blank ...
Page 286: ...This page is intentionally left blank ...
Page 289: ......