Procedure
1. Open the door. Refer to section
2. Loosen the fasteners (A).
3. Move the sliding plates (B) to open the
cable inlets.
9.4
Guide the cables to the cabinet
Preliminary requirements
1.
The cable inlets are open.
Procedure
1. Guide the AC input cable, DC auxiliary
cable, interlock and CAN cables (A)
through the opening (B).
2. Guide the DC output cables (C)
through the opening (D).
9.5
Close the cable inlets
Preliminary requirements
•
Torque wrench
B A
C D
A
B
Mechanical installation of the power cabinet
46