Procedure
1. Guide the cable (A) to the switch
ethernet device (B).
2. Connect the RJ45 plug to the switch
port X1 (C).
8.8
Connect the control cable for the tilt sensors from the
external customer interface to the charge post (option)
Preliminary requirements
•
Torque screwdriver, cross
•
Wire cutter
•
Wire stripper pliers
•
Crimp pliers
•
Control cable for the tilt
sensors. Refer to section
•
Ferrules
Procedure
1. Strip the insulation from the ends of
the wires (A) to (D). For the
specification, refer to section
.
2. Crimp ferrules onto the end of the
wires.
3. Loosen the screws of the terminal
block X-20.
4. Connect these wires:
•
V- wire (A), grey, to the terminal
X-20-4 (E)
•
V+ wire (B), blue, to the terminal
X-20-5 (F)
•
Rin wire (C), green, to the terminal
X-20-6 (G)
•
Rout wire (D), brown, to the terminal X-20-7 (H)
5. Tighten the screws to the correct torque. For the specification, refer to section
A
B
C
C
A
D
B
H F E G
Electrical installation of the charge post
9AKK107992A6488-EN | 004
61